HomeMy WebLinkAbout316153_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101119407
PROJECT ADDRESS:
1011 E St Gertrude Pl Unit# 2
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/28/2024
INITIAL REVIEW
6/10/2024
EXPIRATION
11/24/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
George Castillo
3.
TEL:
(714)528-2900
FAX:
VALUATION:
EMAIL:
gabrielle@vincorinc.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2022California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.Comments have been provided on drawing and calculation hard copies in relation to all comments below. Applicant must pick up red marked sets from city prior to resubmittal and return marked up set with resubmittal.DrawingsSheet S1.2Fix graphical issue found on various sheets at title block. Sheet S2.0Applicant shall verify existing foundation occurs. This revision submittal has been applied due to no existing foundation being found during inspection. EOR shall revise design and drawings to incorporate no existing continuous foundation and provide the required revision for new foundation. This new design for ADU does not currently fix issue found in field. PC #2: Please note that this original ADU is unpermitted. Therefore, all items are not considered “existing”. Information for all items shall be provided as if newly built. This includes slab on grade thickness, rebar, etc..However, for construction and detailing purpose, this can be labeled as existing unpermitted. For example, detail 9/S3.0 shall can show existing unpermitted slab on grade to be doweled into new foundation.Additional CommentsSheet S2.0Calculations spec HDU4 holdowns for all shearwalls. Revise to match calculations.Sheet S3.0Detail 9 – Footings shall be doweled into existing unpermitted slab on grade.(End of Comment)