HomeMy WebLinkAbout318866_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101120304
PROJECT ADDRESS:
1538 W Occidental St
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/6/2024
INITIAL REVIEW
8/7/2024
EXPIRATION
2/2/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Thomas Aldana
3.
TEL:
(714)412-5612
FAX:
VALUATION: $30,000.00
EMAIL:
tomaldana@gmail.com
FLOOD ZONE: X-0602320257J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2022 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Applicant shall obtain clearance/approvals from following departments after obtaining approval from Building and Safety Division, prior to building permit issuance
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☐Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).
Applicant must pick up red marked sheet from the City prior to resubmittal and return the marked up set with resubmittal
PLAN REVIEW COMMENTS:
Provide construction detail for eaves projection – Provide one-hour protection on the underside of eave when eaves projected into the 5-ft of fire separation distance. No projection beyond 2-ft of the fire separation distance. (CRC Table R302.1(1))
Provide construction detail for
Ceiling joist connect to roof rafter and exterior wall where joists are perpendicular to exterior wall
Ceiling joists and roof rafters are parallel to exterior wall
California framing detail – are the intermediate kicker going to provide for roof rafter support? If not, delete from detail. If so, provide
Full detail include how the bottom of kicker support and connection.
Provide schedule per detail note for review
Ridge support detail –
Provide construction detail for how (E) framing wall receiving (N) ridge, including connection
Is there a new framing member under the framed wall? Provide framing size on plan
Red marked comment set is available to pick-up at the City Hall.(End of Comment)