HomeMy WebLinkAbout319313_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101120429
PROJECT ADDRESS:
1009 W River Ln
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/14/2024
INITIAL REVIEW
8/29/2024
EXPIRATION
2/10/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Monika Stamp
3.
TEL:
(714)417-0508
FAX:
VALUATION: $55,000.00
EMAIL:
monikas.direct@aol.com
FLOOD ZONE: AE-0602320144J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
Indicate weight and type of the new stone veneer.Provide specifications and details for stone and masonry veneer in compliance with CRC Section R703.7. Indicate vertical supports for anchored veneer and air spacing in accordance with CRC Section R703.7. D4. Provide specifications for lath, plaster and drywall to conform to the requirements of CRC Chapter 7.Provide moisture barrier detail and attachment detail for wood siding per CRC chapter 7.Engineer of record shall verify the demo’d wall is not bearing r a shear wall.Please revise sheet S1 to match the floor plan.