PLAN CHECK NO:
101120272
PROJECT ADDRESS:
1418 E Fifteenth St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/5/2024
INITIAL REVIEW
8/11/2024
EXPIRATION
2/1/2025
RECHECKS:
1.8/25/2024
PROJECT APPLICANT CONTACT PERSON:
2.
Alex Magana
3.
TEL:
(619)779-0668
FAX:
VALUATION: $35,000.00
EMAIL:
alexmagana59@hotmail.com
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2022California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.
The applicant shall obtain clearances/approvals for the following after obtaining approval from Building and Safety Division, prior to building permit issuance (CHECKED BOXES REQUIRED ONLY):
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. Applicant must pick up red marked sets from city prior to resubmittal and return marked up set with resubmittal.DocumentationPlease coordinate documents between designer and calculations/engineer. Items designed by engineer should be provided on drawings in a clear and precise manner. PC #2: Comment not fully addressed at this time.Provide on the plans, structural material notes (ex. Lumber species & grade, glu-lam beams, concrete (fc’ = ___ psi (min)), steel reinforcement, special inspection requirements, etc.))DrawingsSheet A-1
Provide the following design data on the first sheet (R106.1.1)
☐Sheet Index
☒Occupancy groups (R-3/U)
☒Type of construction (V-B) PC #2: Type of Construction is V-B not VD. Revise note.
☒Automatic Fire Sprinkler (YES or NO)
☒Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☐Floor area per occupancy group, including the existing structure(s)
☒Construction shall comply with the 2022 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.
Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. The Building and Safety Division plan review does not include potential electrical, water, or gas revisions required by any non-city utility company. It is solely on the contractor to ensure proposed addition or alteration can and will meet utility company requirements. MEP are subject to building field inspection.Ensure all hand written items are revised in resubmittal (e.g. Code Reference).Sheet A-3Specify new wall on plan north wall of addition. All new walls and infills shall be specified as new where required.Specify where ceiling height change occurs on plans per sections. Verify lighting to occur at different ceiling elevations as shown on plan. Show location(s) of 22" x 30" attic access with 30" minimum clear headroom in addition. (R807.1)PC #2: Justify not providing attic access in separate attic per section 2022 CRC Section R807.1. New beam in legend does not match linework on framing plan. Revise to match. Sheet A-4Right Elevation – Verify new and existing interaction with Section A-A. Section shows existing and new roof framing to align.Provide FF elevation from grade.Verify crawlspace vents shown at addition. Plans show new slab on grade.PC #2: Specify size of new vents on sheet. Verify where existing crawlspace vent and entry occurs. Any existing vents or entry covered by proposed addition shall be replaced in kind.Sheet A-5Verify on foundation plan where 6’-0” existing footing to remain is noted. If footing to remain, dowel new to existing footing on side where new and existing meet.Remove existing wall that is to be demo’ed on Foundation Plan. Plan shall show finished construction.Provide new footing along plan east and plan south side of addition. Else justify slab on grade support as it cannot be doweled into existing.New Vapor Barrier shall be 10 MIL minimum. Revise on all sheets where Vapor Barrier is mentioned (e.g. Plans, Details, etc…)Sheet A-6Provide ceiling height for new ceiling.Section A-A – Verify wall shown in section between new and existing occurs.Section A-A – Provide detail for existing and new interaction as well as verify roof elevation for new relative to existing.It is recommended to demo existing concrete steps and paving under new addition. Else provide justification for soil between new slab on grade and existing concrete and provide drainage to prevent moisture capture. Section B-B – Verify what 8” dimension shown is for. Sheet A-7Shearwall information provided does not match calculations. Revise to match, else justify change. While adding more shearwall length is better, changing the type, nailing, and holdown requirement from originally designed needs to be justified.PC #2: Response is not adequate. Providing shearwall along entire wall may be better in some cases, however it must still be justified or adequately shown that engineering judgement has been used to provide something better than what is engineered. The wall on the Plan North side full length is longer, but it shall be justified that holdowns is not required as they are originally designed by the engineer. The wall on the Plan West side is NOT adequate replacement to the designed and shall be fully following engineering including shear wall lengths and holdowns. All of these information shall be provided on drawings.Beam sizes shall be provided on framing plan and not legend. Else provide legend on framing plan sheet. Justify support where new hip beams are connected to ridge beam. It is unclear where load path is going. Provide detail for connection. Please reach out to engineer for design.Provide justification for existing foundation supporting new beam between addition and existing. Else provide new foundation for long beam.PC #2: Response is not adequate. Provide calculation justifying existing footing is adequate to support new PSL Beam reactions.Provide roof slope on Roof Plan.Show on the plans - attic vent locations, type and size (area = 1/150 of the attic space). Provide an attic cross ventilation summary; on the plans indicate the total area required versus provided. (R806.1)PC #2: Attic ventilation calculation not provided. Calculation shall be shown on drawings as well as proposed ventilation meeting required. There is no ventilation information found.Sheet A-10Specify where sections provided occurs on plan. It is unclear what is shown on this sheet. Sheet D-1Various details are illegible. Dimensions, notes, and visuals shall be clear and concise.Remove repeated or unused details. (e.g. Detail 7, Detail 18 repeats Detail 11, etc…)Detail 1 – New foundation shall be 18” embedded from lowest adjacent grade. Embedment shall be dimensioned from lowest grade on detail.Detail 1 – Shearwall schedule noted on detail is not found.Detail 1 – Verify note (N) E.B. 5/8” DIA @ 32” oc. This note does not seem to be pointing towards anything.Detail 2 – Verify note (2) # bars. Detail 6 – Verify transverse bars shown in detail.Sheet D-KProvide detail from new floor joist to new concrete stem wall. Provide calculation for new guard rail system at deck.Specify metal anchor shown at pre-fabricated block.Fix dimensions on Deck Framing Plan – dimensions do not look to be pointing at items in various locations. PC #2: Dimensions still not pointing to anything at various locations. CalculationsProvide plan or reference on drawings where members that are designed occur. It is unclear where B1, RD1, etc.. occurs. Member sizes shown in design are not found on drawings. It shall be clear and concise where framing occurs and it shall match calculation design, else calculations shall be revised to match drawings. (e.g. BM 1 – (3) 2x10 not found on drawings.PC #2: It is still unclear where RD1 occurs as designed. (2) 2x8 framing not found.Page 16 – Where does Footing F2.0 occur? Footing cannot be found on drawings. If at deck, drawings do not match calculations.PC #2: Footing calculation looks to be for pad footing, verify if this is to occur in project. Page 19 – Justify seismic loading along Line 1. Existing perimeter wall potentially eliminates lateral system for existing mass. New lateral system shall support existing mass unless load is shown to transfer elsewhere. With addition being shown at a higher roof elevation than existing, existing load transfer shall be justified as well. PC #2: Added shearwall above beam does not drag to any lateral system, else confirm interior wall is a shearwall. This is not a sufficient lateral system to carry and transfer existing mass or new mass.Page 19 – It is recommended to add a new shear wall along the south side of addition along existing wall. Else justify Line A loading to potentially support existing mass. Many old houses found to rely on stucco only as lateral system and with stucco removal, could lead to no lateral system.Page 20 – All structural items shall be clearly shown on drawings. Shear wall types not found on drawings and designer looking to call their own system.Page 20 – Holdowns not found on drawings, provide on drawings. PC #2: Holdowns still not found at shearwalls as designed.Page 21 – Drawing does not match calculation, designer looks to be revising intended shear wall, this shall be justified by the engineer of record. PC #2: Comment not fully addressed.Page 21 – Holdown not found on drawings, provide on drawings. PC #2: Holdowns still not found at shearwalls as designed.Additional CommentsSheet A7Shearwall length on each side of opening shall be provided on plan.Detail 6/D1 referenced doesn’t show new holdown or post connection.Sheet A8Window Schedule is cut off at the top, please fix.Sheet D1Detail 5 – New foundation shall be shown to be doweled from lowest adjacent grade. At foundation adjacent to deck, this means the 20” embedment shall be from where the grade below the deck occurs, not below the slab on grade. Revise detail. Detail 5 – Detail 1 shows footing width to be 18”, revise to match. Detail 6 – New footing shall be shown to be adequately doweled into existing foundation, not exterior slab. Sheet DKTwo DK sheets provided, remove extra sheet. Canceled work should be removed from drawings and not just crossed out and shown as canceled for clarity. CalculationsPage 21 – Shearwalls are designed for 3’-0” lengths but drawing sheet A3 specifies 33” wall lengths. Revise calculation as needed. (End of Comment)