PLAN CHECK NO:
101120934 &101120935
PROJECT ADDRESS:
632 S Genoa Dr Unit# -
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
9/25/2024
INITIAL REVIEW
10/21/2024
EXPIRATION
3/24/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Kevin Nguyen
3.
TEL:
(714)951-8540
FAX:
VALUATION: $ 50000
EMAIL:
kevinnguyentda@yahoo.com
FLOOD ZONE: A-06059C0256J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Provide building information on plans:
- Occupancy type: R3 / UShow 30-inch clear width for water closet compartments and 24-inch clearance in front of a water closet. Show location of heating equipment on the plans. (CRC R303.8) Provide carbon monoxide detector for both units. Please see red marks.Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Glass enclosure doors and panels must be labeled Category II. Swing door outward. Net area of shower receptor shall be not less than 1,024 sq. in. of floor area, and encompass 30-inch diameter circle. (CPC411.7)Stairways within dwelling units and exterior stairways serving a dwelling unit shall have an illumination level of not less than 1 foot-candle measured at the center of the treads and landings. (CRC R303.6)Fireblocking is required in concealed spaces 10’ o.c. horizontal, vertically at the ceiling and floor levels, connections between horizontal and vertical spaces, concealed spaces between stair and landing, openings around vents, pipes, ducts, cables, wires, chimneys and fireplaces. (CRC R302.11)( Provide for the fire place)
The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1):
- All plumbing walls are to be framed with a minimum of 6" studs.
- Permissible notching and boring of joists are to be shown on the plans and shall not exceed CBC
Section 2308.10.4.2 allowances.
- Notching of exterior and bearing/nonbearing walls shall not exceed 25%/40% respectively. Bored
holes in bearing/nonbearing walls shall not exceed 40%/60% respectively. In no case shall the
edge of the bored hole be nearer than 5/8 inch to the edge of the stud. (2308.9.10 and 2308.9.11)
- Header and trimmer details for doors and windows are to be shown with full length trimmers,
specifying the size of the header and trimmer. (2308.10.4.3)Show exhaust hood and exhaust vent above cooking appliances at the kitchen. (CMC 504.2) Provide Ufactor and SHGC factor for new windows and doors.A minimum 200 amp service panel is required for all new dwellings. (CEC 230.79(C)) Show all plumbing fixtures comply with California Green Building Code 2022.Provide construction detail for new opening in the new bathroom on the first floor. ( 4x4 beam seems over stressed) Provide roof framing detail for the removed chimney. Provide I-hr fire rating wall between the 2 units, provide detail per CBC 2022. Provide STC rating between 2 units.