PLAN CHECK NO:
101121797
PROJECT ADDRESS:
302 S Newhope St
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/5/2024
INITIAL REVIEW
1/24/2025
EXPIRATION
6/3/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Mike Abbas
3.
TEL:
(818)442-4455
FAX:
VALUATION: $20,000.00
EMAIL:
souria24@yahoo.com
FLOOD ZONE: A-06059C0256J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
Sheet SP: Please show separation distance between the deck to adjacent existing building.
Due to the exterior wall protection requirement based on the fire-separation distance, the proposed posts and beams are not allowed.
Sheet A1-A3: Due to the exterior wall protection requirement based on the fire-separation distance, the proposed posts and beams supporting existing cantilevered balconies are not allowed. Please revise plans accordingly.
New guardrail with siding at balcony: Please provide/show openings for drainage from balcony. Provide detail.
Sheet S2: Structural review for the balconies were not proceed due to fire-separation setback comment above.
(End of comment)