Loading...
HomeMy WebLinkAbout319255_2_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101120415 PROJECT ADDRESS: 3019 S Manitoba Dr Unit# 2 PLAN CHECK ENGINEER: Lo, JonathanTEL:714 647-5822 EMAIL: Jlo@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-3 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 8/13/2024 INITIAL REVIEW 9/6/2024 EXPIRATION 2/9/2025 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Victor Rios 3. TEL: (714)788-9836 FAX: VALUATION: $49,000.00 EMAIL: vicrios9620@gmail.com FLOOD ZONE: X-06059C0259J Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment. The applicant shall obtain clearances/approvals for the following after obtaining approval from Building and Safety Division, prior to building permit issuance (CHECKED BOXES REQUIRED ONLY): ☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. ☒Public Works Agency approval (647-5039). ☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700). ☒Police Department approval on the corrected/final set of drawings (647-5840). ☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work. ☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance. ☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. Applicant must pick up red marked sets from city prior to resubmittal and return marked up set with resubmittal.DrawingsSheet 1 Provide the following design data on the first sheet (R106.1.1) ☐Sheet Index ☐Occupancy groups (R-3/U) ☐Type of construction (V-B) ☐Automatic Fire Sprinkler (YES or NO) ☐Number of stories. ☒Flood Zone: X ☐Flood Zone: A ☐Flood Zone: AE ☐Floor area per occupancy group, including the existing structure(s) ☐Construction shall comply with the 2022 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions. Please provide new ADU square footage to existing single family residence square footage ratio (ADU sf / SFD sf) on the Cover Sheet.  Square footages shall NOT include garage, non-habitable attic space, non-habitable basement space, patio cover, patio enclosure, sunroom and similar uses.Note the following on cover sheet:ADU / SFD = ____sf / ____ sf = ____% The ADU sf / SFD sf ratio is for Park & Rec fee purpose only. The applicant is responsible for the given “SFR sf” of the existing primary residence; Building Safety staff are not responsible for the accuracy of the given “SFR sf”. Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. The Building and Safety Division plan review does not include potential electrical, water, or gas revisions required by any non-city utility company. It is solely on the contractor to ensure proposed addition or alteration can and will meet utility company requirements. MEP are subject to building field inspection.Sheet 7 for Title 24 not provided. Title 24 shall be provided in drawing set.Ensure all hand written items is corrected in resubmittal (e.g. Code Reference, Unit #2, etc..)Sheet 2 Walls separating dwelling units (main house and new ADU) shall be minimum 1-hour fire partition. Fire rated floor-ceiling and wall assemblies shall extend to and be tight against the exterior wall, and wall assemblies shall extend from the foundation to the underside of the roof sheathing. Provide details on the plans. (R302.3 CRC) Walls separating dwelling units shall provide airborne sound insulation for walls with an STC rating of at least 50 per. Provide details on plans and provide verification of a tested assembly to achieve the required STC rating of 50. Through penetrations of fire-resistance-rated wall or floor assemblies shall comply with Section R302.4.1.1 or R302.4.1.2. (R302.4) Show location(s) of 22" x 30" attic access with 30" minimum clear headroom. (R807.1)Provide required minimum airflow for new kitchen range hood on plan per 2022 California Energy Code. On the plan, provide a landing or floor on each side of each exterior door. Landing shall have width of not less than the door served and a minimum of 36” measured in the direction of travel.Show ductless minisplit and any new condenser location on plan. The following Electric Ready notes shall be added and constructed for new detached residential structures: Water Heating system (water heater) – (Section 150.0(n)) Systems using gas or propane water heaters to serve individual dwelling units shall designate a space at least 2.5 feet by 2.5 feet wide and 7 feet tall suitable for the future installation of a heat pump water heater (HPWH) by meeting either A or B listed under Section 150.0(n). If the designated space is within 3 feet from the water heater: A dedicated 125 volt, 20 amp electrical receptacle that is connected to the electric panel with a 120/240 volt 3 conductor, 10 AWG copper branch circuit, within 3 feet from the water heater. ii. Isolate both ends of the unused conductor. A reserved single pole circuit breaker space in the electrical panel adjacent to the circuit breaker A condensate drain that allows natural draining of the water heater. . If the designated space is more than 3 feet from the water heater: see additional Code requirements. When a second water heater is installed as part of the addition shall comply with Section (150.2(a)(D). Sheet 3Specify all new finish types on elevations. It is unclear. Veneer – On the plan, please specify manufacturer’s name, and ICC report number of the veneer. Provide detail attachment of veneer. Show on the plans - attic vent locations, type and size (area = 1/150 of the attic space). Provide an attic cross ventilation summary; on the plans indicate the total area required versus provided. (R806.1)Sheet 4Braced wall panel on west wall shall be designed as BV-WSP for brick veneer [R602.10.4]. Minimum sheathing and nailing shall be met or better. Minimum brace wall panel length = 11’-0” [Table R602.10.6.5.4] Revise as needed to meet requirements or provide calculations.Provide detail for non-bearing wall top and bottom connections. Ensure top connection is fully non-load bearing.Provide detail for fire rated and stc rated system between existing unit and proposed ADU. Fire rated system shall span to underside of roof sheathing. Detail 1 - Verify how 8” depth from FF to grade will be accomplished at existing drive way. Existing drive is flush with existing slab. (End of Comment)