PLAN CHECK NO:
101121859
PROJECT ADDRESS:
326 E Grant St Unit# 2
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/11/2024
INITIAL REVIEW
1/28/2025
EXPIRATION
6/9/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Gonzalo Guillen
3.
TEL:
(714)667-0892
FAX:
VALUATION: $125,000.00
EMAIL:
gplanos@sbcglobal.net
FLOOD ZONE: X-06059C0276J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2022 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Applicant shall obtain clearance/approvals from following departments after obtaining approval from Building and Safety Division, prior to building permit issuance
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).
Applicant must pick up red marked sheet from the City prior to resubmittal and return the marked up set with resubmittal
PLAN REVIEW COMMENTS:
Applicant shall address all the checked‘☒’ correction comments below before resubmitting plans to Building Safety for recheck.
☒1. Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.
☒2. Add note on the coversheet: Minimum 2.04(KW) photovoltaic system will be submitted under a separate permit and shall be issued prior to building frame inspection request.
☒3. Exterior walls without Automatic Residential Fire Sprinkler – (Table R302.1(1))
Exterior walls located less than 5-ft from a property line shall be of one hour construction.
Exterior walls located less than 3-ft from a property line – No opening shall be provided.
Wall between 3-ft and 5-ft of the property line – 25% of wall openings are permitted.
Eaves projection – Provide one-hour protection on the underside of eave when eaves projected into the 5-ft of fire separation distance. No projection beyond 2-ft of the fire separation distance.
☒4. Show/provide safety glass in hazardous locations (R308) –
☒Glazing in enclosure for or walls facing hot tubs, bathtubs, showers, whirl-pools, saunas, steam rooms where the bottom edge of the glazing is less than 60” above the any standing surface.
☒5. Roofing requirements – (R901)
☒Cool roof is required. On the plan, specify CRRC #.
☒6. Aging-in-place Design & Fall Prevention – (R327)
☒Reinforcement for grab bar: at least one bathroom on the entry level shall be provided with reinforcement installed. Where there is no bathroom on the entry level, at least one bathroom on the second or third floor of dwelling shall comply
Reinforcement shall be solid lumber or other construction materials approved by the enforcing agency.
Reinforcement shall not be less than 2x8 inches nominal lumber or other construction material provide equal height and load capacity. Reinforcement shall be located between 32 inches and 39 ¼ inches above the finished floor flush with the wall framing
Water closet reinforcement shall be install on both side walls of the fixture, or one side wall and the back wall
Shower reinforcement shall be continuous where wall framing is provided
Bathtub and combination bathtub/shower reinforcement shall be continuous on each end of the bathtub and the back wall. Additionally, back wall reinforcement for a lower grab bar shall be provided with the bottom edge located no more than 6 inches above the bathtub rim
☒Electrical receptacle outlet, switch and control height: Electrical receptacle outlets, switches and control (including controls for heating, ventilation and air conditioning) intended to be used by occupants shall be location no more than 48 inches measured from the top of the outlet box and not less than 15 inches measured form the bottom of the outlet box above the finish floor
☒Doorbell buttons: doorbell buttons or controls, when installed, shall not exceed 48 inches above exterior floor or landing, measured from the top of the doorbell button assembly. Where doorbell buttons integrated with other features are required to be installed above 48 inches measured from the exterior floor or landing, a standard doorbell button or control shall also be provided at a height not exceed 48 inches above exterior floor or landing, measure from the top of the doorbell button or controls.
Energy Conservation – Title 24 Energy forms & calculations
☒7. Water Heating system (water heater) – (Section 150.0(n)) Systems using gas or propane water heaters to serve individual dwelling units shall designate a space at least 2.5 feet by 2.5 feet wide and 7 feet tall suitable for the future installation of a heat pump water heater (HPWH) by meeting either A or B listed under Section 150.0(n).
A. If the designated space is within 3 feet from the water heater:
i. A dedicated 125 volt, 20 amp electrical receptacle that is connected to the electric panel with a 120/240 volt 3 conductor, 10 AWG copper branch circuit, within 3 feet from the water heater.
ii. Isolate both ends of the unused conductor.
iii. A reserved single pole circuit breaker space in the electrical panel adjacent to the circuit breaker
iv. A condensate drain that allows natural draining of the water heater.
B. If the designated space is more than 3 feet from the water heater: see additional Code requirements.
When a second water heater is installed as part of the addition shall comply with Section (150.2(a)(D).
Additional Review Comments:
Sheet A1:
Update sheet index
Sheet A2:
Floor plan key notes #15, verify detail reference. Should it be 5/A5
Sheet A3
Section A: Collar tie to be located in the upper third of the attic space
Section B: Collar tie to be located in the upper third of the attic space
Sheet A4
Porch columns (4 total) are cantilever columns. EOR to provide calculation to justify moment at the base is capable to transfer to footing. Provide construction detail for moment base footing
Sheet A5
Detail 12
Provide shear transfer from 2x blk at top and bottom of the cripple stud
Prior to submit the hard-copy drawings for approval and permit issuance. It is at applicant’s discretion, as an option, to submit a full-set electronic drawing (in pdf format) for a courtesy review. Please include the original red-marked comment drawing set, red-marked calculation, and all supporting document (revised calculation, etc.) for an expedite review.
Red marked comment set is available to pick-up at the City Hall.