HomeMy WebLinkAbout324664_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
104122208
PROJECT ADDRESS:
2625 S Hickory St
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830
EMAIL:
aso@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
III B
OCCUPANCY CLASSIFICATION(S):
B, F-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/21/2025
INITIAL REVIEW
2/24/2025
EXPIRATION
7/20/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
David Chacon
3.
TEL:
(562)912-4884
FAX:
VALUATION: $11,500.00
EMAIL:
dchacon@dcdbc.net
FLOOD ZONE: X-06059C0278J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Please return marked up set of drawings with corrections.
GENERAL REQUIREMENTS
Obtain any applicable approval from the following agencies prior to permit issuance:
Planning Division – The plans approved by the Building Division must include the Planning approval stamp. Building staff will notify the Planning Division for approval. For approval status, contact the Planning Division at (714) 647-5804 or visit the Planning Division counters.
Public Works Agency (PWA) – Obtain PWA clearance if any of the following applies: project valuation exceeds $30,000, project has added plumbing fixtures, added bedrooms, or project exceeds 500 square foot in new construction (not renovation). After the Building Division approves your project, visit the Building Division counters and request a copy of the approved plan. Bring the approved plan to the PWA counters for approval. After PWA approves your project, return the approved plan to the Building Division counters.
Police Department (PD) – The plans approved by the Building Division must include the PD approval stamp. After the Building Division approves your project, Building staff will notify PD for approval. For approval status, contact the PD at (714) 647-5840 or email PolicePlanCheck@santa-ana.org.
Orange County Fire Authority (OCFA) - Submit plans to OCFA immediately if you answer “Yes” to any part of questions 1 through 10 on the plan submittal criteria. Bring an OCFA approved plan to the Building Division counters for permit issuance. Contact OCFA for approval status.
County of Orange, Health Care Agency, Environmental Health (OC Health) – Submit plans to OC Health if the business involves food service. Contact OC Health for submittal requirements. If OC Health approval is required, bring an OC Health approved plan to the Building Division counters for permit issuance.
School District – After the Building Division approves your project, Building staff will send a School Fee Form to your school district if school fee applies to your project. Applicant shall pay the school fee and bring the signed Certificate of Compliance form to the Building Division counters for permit issuance.
Cal/OSHA – Check the Cal/OSHA permit requirements here.
This plan check will expire after 180 days from the submittal date unless the applicant request for an extension. The extension request must be in writing and demonstrate a justifiable cause. The Building Official is authorize to grant a one-time extension of additional 180 days. If the extension request is approved, all plan checks will expire after 360 days from the submittal date. No further extension will be granted after 360 days from the submittal date.
This review does not include Mechanical, Electrical, and Plumbing (MEP).
Apply for MEP permits for the walk-in cooler. Refer to Handout BLD-27 for specific requirements.
Additional plan check fee will be required after the third review on hourly basis.
The stated valuation appears low. Provide justification by submitting a detailed cost breakdown, a contractor's estimate, or referencing ICC Building Valuation Data based on construction type and occupancy.
INSTRUCTIONS
Plan Check Comments Instructions - Review all corrections and provide a written response.
Redline Pickups Instructions - The drawings markups (Redlines) are available to pick up at the Building Division counters by walk-ins. Appointments are not required. Our business hour is Monday through Thursday and alternative Fridays from 8:00 am to 3:00 pm. See the Holiday and Closed Friday Schedule before you plan your visit.
Resubmittal Instructions – Provide a written response to the Plan Check Comments. Provide two copies of the latest construction document (drawings, calculations, and others related document). Provide one additional copy of drawings for new constructions or additions. Resubmit all construction document with one of the three options below:
Resubmittal Bin:Complete the Plan Check Re-Submittal Form along with the resubmittal. The resubmittal bin is available at the City Hall Ross Annex lobby, Monday through Thursday and alternating Fridays from 8:00 am – 4:00pm. See the Holiday and Closed Friday Schedule before you plan your visit.
Walk-ins: Daily walk-ins are available for resubmittals at first come first serve basis. Please note all scheduled appointments will be served first prior to any walk-ins.
Appointment: Call the Building division at 714-647-5800 to schedule a resubmittal appointment, or contact your assigned permit counter staff for your specific project.PLAN REVIEW COMMENTSSheet T1.0Add structural sheets to the sheet index.Under the related permit section, provide a note indicating that all code violation-related items for building permits must be issued simultaneously, including the storage rack.List the mechanical-electrical-plumbing (MEP) permits for the walk-in cooler under the related permit section.Sheet A1.0On Detail Number 4, specify the dowel size, the spacing, the embedment, the type of epoxy used, and the ICC number.On Detail Number 4, specify the redhead's diameter, spacing, and embedment.Sheet A2.0Delete all the notes and details called out as not applicable to this project, such as cross-section details and the grab-bar notes. These are not applicable items for this project.On the floor plan, cross-reference detail 2/A1.0 for the concrete pad.
Verify that the existing roll-up door is not a required exit door. On the floor plan, show all exits and ensure that the total number of exits meets the requirements and that the travel distance(s) are met.
Show the number of required exits and provided exits in the warehouse, and show the travel distances to the exits.The floor plan shows a new block wall; however, the wall legend indicates an 8-inch concrete wall. Resolve the discrepancy.Structural SheetsMake a note on all the structural sheets as "For reference only."The End.