HomeMy WebLinkAbout323367_3_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101121797 PROJECT ADDRESS: 302 S Newhope St PLAN CHECK ENGINEER: Le, TungTEL:714 647-5896 EMAIL: Tle10@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-2 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 12/5/2024 INITIAL REVIEW 1/24/2025 EXPIRATION 6/3/2025 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Mike Abbas 3. TEL: (818)442-4455 FAX: VALUATION: $20,000.00 EMAIL: souria24@yahoo.com FLOOD ZONE: A-06059C0256J Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: -Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. Sheet SP: Please show separation distance between the deck to adjacent existing building. Due to the exterior wall protection requirement based on the fire-separation distance, the proposed posts and beams are not allowed. 2nd Review Comment: Floor plans – Plans were mislabeled bedroom as closet. Please revise plans to label Existing (E) bedroom. New guardrail with siding at balcony: Please provide/show openings for drainage from balcony. Provide detail. 2nd Review Comment: Detail 8/SD2 – Please specify/show openings for drainage. Sheet S2: Structural review for the balconies were not proceed due to fire-separation setback comment above. 2nd Review Comment: Deck framing referenced details – Please revise plans referencing to Sheet SD2 for deck framing details. (End of comment)