PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101121062 & 101121063
PROJECT ADDRESS:
811 N Broadway
PLAN CHECK ENGINEER:
So, Anson
TEL:714
647-5830
EMAIL:
aso@santa-ana.org
FAX:714
647-5897
TYPE OF CONSTRUCTION:
I A
OCCUPANCY CLASSIFICATION(S):
A-3, M, R-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/16/2023
INITIAL REVIEW
10/17/2023
EXPIRATION
4/13/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
William Beaubeaux
3.
TEL:
(714)240-2739
FAX:
VALUATION: $5,400,000.00
EMAIL:
wbeaubeaux@gmail.com
FLOOD ZONE: X-0602320163J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan-check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Resubmit two corrected sets of plans.
Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.
GENERAL REQUIREMENTS
Clearances - Obtain any applicable approval from the following agencies prior to permit issuance:
Planning Division – The plans approved by the Building Division must include the Planning approval stamp. Building staff will notify the Planning Division for approval. For approval status, contact the Planning Division at (714) 647-5804 or visit the Planning Division counters.
Public Works Agency (PWA) – Obtain PWA clearance if any of the following applies: project valuation exceeds $30,000, project has added plumbing fixtures, added bedrooms, or project exceeds 500 square foot in new construction (not renovation). After the Building Division approves your project, visit the Building Division counters and request a copy of the approved plan. Bring the approved plan to the PWA counters for approval. After PWA approves your project, return the approved plan to the Building Division counters.
Police Department (PD) – The plans approved by the Building Division must include the PD approval stamp. After the Building Division approves your project, Building staff will notify PD for approval. For approval status, contact the PD at (714) 647-5840 or email PolicePlanCheck@santa-ana.org.
Orange County Fire Authority (OCFA) - Submit plans to OCFA immediately if you answer “Yes” to any part of questions 1 through 10 on the plan submittal criteria. Bring an OCFA approved plan to the Building Division counters for permit issuance. Contact OCFA for approval status.
County of Orange, Health Care Agency, Environmental Health (OC Health) – Submit plans to OC Health if the business involves food service. Contact OC Health for submittal requirements. If OC Health approval is required, bring an OC Health approved plan to the Building Division counters for permit issuance.
School District – After the Building Division approves your project, Building staff will send a School Fee Form to your school district if school fee applies to your project. Applicant shall pay the school fee and bring the signed Certificate of Compliance form to the Building Division counters for permit issuance.
Cal/OSHA – Check the Cal/OSHA permit requirements here.
Plan Check Expiration – This plan check will expire after 180 days from the submittal date unless the applicant request for an extension. The extension request must be in writing and demonstrate a justifiable cause. The Building Official is authorize to grant a one-time extension of additional 180 days. If the extension request is approved, all plan checks will expire after 360 days from the submittal date. No further extension will be granted after 360 days from the submittal date.
MEP Reviews – This review does not include Mechanical, Electrical, and Plumbing (MEP).
Additional plan check fee will be required after the third review on hourly basis.
INSTRUCTIONS:
Plan Check Comments Instructions - Review all corrections and provide a written response.
Redline Pickups Instructions - The drawings markups (Redlines) are available to pick up at the Building Division counters by walk-ins. Appointments are not required. Our business hour is Monday through Thursday and alternative Fridays from 8:00 am to 3:00 pm. See the Holiday and Closed Friday Schedule before you plan your visit.
Resubmittal Instructions – Provide a written response to the Plan Check Comments. Provide two copies of the latest construction document (drawings, calculations, and others related document). Provide one additional copy of drawings for new constructions or additions. Resubmit all construction document with one of the three options below:
Resubmittal Bin:Complete the Plan Check Re-Submittal Form along with the resubmittal. The resubmittal bin is available at the City Hall Ross Annex lobby, Monday through Thursday and alternating Fridays from 8:00 am – 4:00pm. See the Holiday and Closed Friday Schedule before you plan your visit.
Walk-ins: Daily walk-ins are available for resubmittals at first come first serve basis. Please note all scheduled appointments will be served first prior to any walk-ins.
Appointment: Call the Building division at 714-647-5800 to schedule a resubmittal appointment, or contact your assigned permit counter staff for your specific project.
Third Plan Check Comment
Where a change of use occurs from commercial to residential, the residential energy provisions must comply with applicable standards. Provide energy documentation for the envelope design, including insulation ratings for walls, U-factors, and solar heat gain coefficients for windows. Demonstrate compliance with energy standards.
Fourth Plan Check Comment: Second Request.
Fifth Plan Check Comment: Third Request.
Sixth Plan Check Comment:
Per email correspondence, the proposed design approach is acceptable.
Please add the following note to the title sheet:"The existing exterior walls and openings (windows, doors) remain unchanged. This project complies with the California Energy Code, Section 180.2 – Alteration."
Sheet A-0.1
Allowable Exterior Wall Openings
The fire separation distance (FSD) on the north side is 5 feet, on the east side is 10 feet 1 inch, and on the south side is 5 feet. Based on the exterior wall opening limitations outlined in the CBC Table 705.8, it appears that the number of openings may exceed the allowable limits. Please provide calculations to demonstrate compliance with the following:
For FSDs ranging from 5 feet to less than 10 feet, the maximum allowable opening is 25%.
For FSDs ranging from 10 feet to less than 15 feet, the maximum allowable and protected opening is 45%.
Provide detailed calculations to show compliance with the code requirements.
Fifth Plan Check Comment: Show the opening calculations on sheet A8:
North Elevation (The 2nd floor, 3rd floor, 4th floor, 5th floor, and the 6th floor have the same amount of opening)
Story wall area = 115’ x 12’ = 1380 sqft
Opening area = 50’ x 9’ = 450 sqft
% opening = 450/1380 = 0.33 (33% > 25%) justification required.
South Elevation (The 2nd floor, 3rd floor, 4th floor, 5th floor, and the 6th floor have the same amount of opening)
Story wall area = 115’ x 12’ = 1380 sqft
Opening area = 39’ x 7’+6+12 = 291 sqft
% opening = 291/1380 = 0.21 (21% < 25%) therefore opening on South elevation is within code limit.
East Elevation (The 2nd floor, 3rd floor, 4th floor, 5th floor, and the 6th floor have the same amount of opening)
Story wall area = 52’ x 12’ = 624 sqft
Opening area = 21’x7’ + 7’x7’ = 196 sqft
% opening = 196/624 = 0.31 (31% < 45%) therefore opening on East elevation is within code limit.
Sixth Plan Check Comment: Please note on the title sheet: "An ingress access easement shall be recorded prior to building permit final."
The minimum gurney size must be 24" x 84”, and the elevator cab dimensions are smaller than required per Figure 1. The elevator does not meet the stretcher requirements. (3002.4.1a)
Fifth Plan Check Comment: The fire report shall address this item. Provide a letter from the OCFA approving the reduced gurney size.
Sixth Plan Check Comment: Pending OCFA approval.
End of Comments