HomeMy WebLinkAbout328592_4_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
104123546
PROJECT ADDRESS:
1327 E St Gertrude Pl
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B, S-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/29/2025
INITIAL REVIEW
5/10/2025
EXPIRATION
10/26/2025
RECHECKS:
1.6/11/25
PROJECT APPLICANT CONTACT PERSON:
2.7/1/25
Spencer Nagel
3.
TEL:
(949)636-3299
FAX:
VALUATION: $10,000.00$ 26,250
EMAIL:
spencer@marvistaconstruction.com
FLOOD ZONE: X-06059C0276J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.Pending 6/11/25The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basiOk 6/11/25Provide complying exiting plan for the “reminder” complete area. Note the use of adjacent units. Pending Enlarge floor plan. Pending 6/11/25 OK 7/1/25Complete the attached Disabled Accessibility Documentation Form. Ok 6/11/25CBC Section 402.8.8 Security grilles and doors. Horizontal sliding or vertical security grilles or doors, which are part of a required means of egress, shall conform to the following:Ok 6/11/25
- They must remain secured in the full open position during the period of occupancy by the general public.
- Doors or grilles shall not be brought to the closed position when there are more than 10 persons occupying
spaces served by a single exit or 50 persons occupying spaces served by more than one exit.
- The doors or grilles shall be openable from within without the use of any special knowledge or effort when the
space is occupied.
- When two or more exits are required, not more than one half of the exits may be equipped with horizontal
sliding or vertical rolling grilles or doors.
- Note on Drawings: Post a legible sign at security grill/door closing controls stating “Security grill/door shall
remain secured in the full open position during the period of occupancy by the general public.”Show all exit doors on the site plan.Pending 6/11/25 Enlarge planProvide complete construction detail to support the roll up door. Pending 6/11/25 See comments 15 and after.Provide weight of the roll up door on the drawings.Ok 6/11/25 6/11/25Provide complete planview and construction detail for the rollup door.Show location of the posts /steel tube on plan view.Sheet S-3, steel tubes (posts) cannot be supported by truss joists, provide engineering calculation.Sheet S-3, please identify the location of concrete wall on the floor plan.How is steel tube supported at the bottom with anchors, is it a saddle or the tube itself anchored to the ground. Provide complete detail.(show how steel tube is connected to the saddle )Show thickness of the footing at the bottom of the tube.Provide complete calculation, show how the tubes are supported by truss.Sheet S-2, identify size and calculation to justify that one screw can support 700lb roll up door to the steel postsComments 15-22 Details shall be stamped by engineer of record. 7/1/25