HomeMy WebLinkAbout330200_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101124009
PROJECT ADDRESS:
916 W Myrtle St Unit# 1
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/13/2025
INITIAL REVIEW
7/25/2025
EXPIRATION
12/10/2025
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Araceli Maciel
3.
TEL:
(714)285-1121
FAX:
VALUATION: $45,000.00
EMAIL:
aramaci65@gmail.com
FLOOD ZONE: X-06059C0257J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2022 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Applicant shall obtain clearance/approvals from following departments after obtaining approval from Building and Safety Division, prior to building permit issuance
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).
Applicant must pick up red marked sheet from the City prior to resubmittal and return the marked up set with resubmittal
PLAN REVIEW COMMENTS:
Sheet A-1
Please verify. Provided package has 2 sheets of A-8. Should one of the sheet number be AD-1?
Please update occupancy group to R-3
Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.
For the purpose of Park & Rec Development fee calculation, please provide new ADU square footage to existing single family residence square footage ratio (ADU sf / SFD sf) on the Cover Sheet. Square footages shall NOT include garage, non-habitable attic space, non-habitable basement space, patio cover, patio enclosure, sunroom and similar uses. Please provide two (2) separate numbers for
ADU to existing single family residence
JADU to existing single family residence
Note on plan: The ADU sf / SFD sf ratio is for Park & Rec fee purpose only. The applicant is responsible for the given “SFR sf” of the existing primary residence; Building Safety staff are not responsible for the accuracy of the given “SFR sf”.
Sheet A-3
Please provide dimension between two dowelling from each side of the imaginary line
Reference detail on plan for
Underside of eave overhang fire rated detail where overhang projected into 5’-0” separation. No overhang is allowed within 2’-0” from the property line
Fire rated wall detail where exterior wall is less than 5’-0” from the property line
Sheet A-5
Provide dimension for the depth of W/H for the JADU building
Provide dimension of the wall length from the main entrance of the JADU building. Tempered glass is required where the window is located less than 2’-0” from the door
Tempered glass is required at (N) family room French swing door
Sheet A-6
Exterior walls without Automatic Residential Fire Sprinkler – (Table R302.1(1))
Wall between 3-ft and 5-ft of the property line – 25% of wall openings are permitted.
Sheet A-7
Under-floor access and ventilation
Provide accesses to all under-floor spaces. On the plan, show locations of under-floor accesses – Access opening through the floor shall be 18”x24” minimum; openings through a perimeter wall shall be not less than 16”x24”. (R408.4)
Show on the plans – under-floor vent locations, type and size (area = 1/150 of the under-floor space). Locate openings at corners and provide cross ventilation. Provide a cross ventilation summary; on the plans indicate the total area required versus provided. (R408.1)
Sheet U-1
Smoke Alarms – Provide smoke alarm(s) in each sleeping room; in each area giving access into each sleeping room; in basement and habitable attics. (R314)
Carbon Monoxide Alarms – Provide carbon monoxide alarms at outside of each sleeping area, in the immediate vicinity of the bedroom(s); on every level of a dwelling unit including basements. (R315)
Water Heating system (water heater) – (Section 150.0(n)) Systems using gas or propane water heaters to serve individual dwelling units shall designate a space at least 2.5 feet by 2.5 feet wide and 7 feet tall suitable for the future installation of a heat pump water heater (HPWH) by meeting either A or B listed under Section 150.0(n).
If the designated space is within 3 feet from the water heater:
A dedicated 125volt, 20amp electrical receptacle that is connected to the electric panel with a 120/240 volt 3 conductor, 10 AWG copper branch circuit, within 3 feet from the water heater.
Isolate both ends of the unused conductor.
A reserved single pole circuit breaker space in the electrical panel adjacent to the circuit breaker
A condensate drain that allows natural draining of the water heater.
If the designated space is more than 3 feet from the water heater: see additional Code requirements.
When a second water heater is installed as part of the addition shall comply with Section (150.2(a)(D).
Sheet U-2
Smoke Alarms – Provide smoke alarm(s) in each sleeping room; in each area giving access into each sleeping room; in basement and habitable attics. (R314)
Carbon Monoxide Alarms – Provide carbon monoxide alarms at outside of each sleeping area, in the immediate vicinity of the bedroom(s); on every level of a dwelling unit including basements. (R315)
Water Heating system (water heater) – (Section 150.0(n)) Systems using gas or propane water heaters to serve individual dwelling units shall designate a space at least 2.5 feet by 2.5 feet wide and 7 feet tall suitable for the future installation of a heat pump water heater (HPWH) by meeting either A or B listed under Section 150.0(n).
If the designated space is within 3 feet from the water heater:
A dedicated 125volt, 20amp electrical receptacle that is connected to the electric panel with a 120/240 volt 3 conductor, 10 AWG copper branch circuit, within 3 feet from the water heater.
Isolate both ends of the unused conductor.
A reserved single pole circuit breaker space in the electrical panel adjacent to the circuit breaker
A condensate drain that allows natural draining of the water heater.
If the designated space is more than 3 feet from the water heater: see additional Code requirements.
When a second water heater is installed as part of the addition shall comply with Section (150.2(a)(D).
Sheet S-1
Provide re-entrance detail between (E) SFR and (N) RM addition at the family room roof
Sheet S-2
Provide reference detail on plan for top plate splice
Prior to submit the hard-copy drawings for approval and permit issuance. It is at applicant’s discretion, as an option, to submit a full-set electronic drawing (in pdf format) for a courtesy review. Please include the original red-marked comment drawing set, red-marked calculation, and all supporting document (revised calculation, etc.) for an expedite review. (End of Comment)