HomeMy WebLinkAbout325363_5_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101122406, 07
PROJECT ADDRESS:
1806 and 1808 W Twenty-First St
PLAN CHECK ENGINEER:
Lee, WayneTEL:714
647-5848
EMAIL:
wlee@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/5/2025
INITIAL REVIEW
3/7/2025
EXPIRATION
8/4/2025
RECHECKS:
1.6/10/20254. 9/23/2025
PROJECT APPLICANT CONTACT PERSON:
2.7/23/2025
Daniel Salmeron
3.8/21/2025
TEL:
(323)443-5749
FAX:
VALUATION: $34,026.27 and $40,000.00
EMAIL:
salmerondrafting@yahoo.com
FLOOD ZONE: X-06059C0144J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.All items noted on this plan check report must be addressed.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.
PLAN CHECK COMMENTS
Provide assembly details on the north side of the new exterior wall. Clarify weather protection on this wall.
STRUCTURAL
Main house. Provide engineering justification to verify the existing interior wall to convert back to new exterior wall to support lateral in-plane shear and out-of-plane forces. Provide framing, foundation and connection details on plan for this wall.
PC5:
Sheet T-3 and SD-1 must be stamped, signed and dated by a licensed engineer.
See sheet T-3. The footing detail 1/T-3 is not available.
See sheet T-3. Detail 1/SD1 refers to added holdown is not available on the foundation plan.
See sheet T-3. The foundation footnote shows existing continuous footing depth to be verified. Provide engineering footing width, depth and reinforcement on plan for field verification.
END OF COMMENTS