HomeMy WebLinkAbout334033_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101125164
PROJECT ADDRESS:
222 W Murphy Ave
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/2/2025
INITIAL REVIEW
11/4/2025
EXPIRATION
3/31/2026
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jorge Gazzoni
3.
TEL:
(714)609-4321
FAX:
VALUATION: $25,000.00
EMAIL:
jorgegazzoni@yahoo.com
FLOOD ZONE: X-06059C0278J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2022 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Applicant shall obtain clearance/approvals from following departments after obtaining approval from Building and Safety Division, prior to building permit issuance
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☐Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).
Applicant must pick up red marked sheet from the City prior to resubmittal and return the marked up set with resubmittal
PLAN REVIEW COMMENTS:
Sheet S2.0
Detail 2/S3.0 show (N) footing is required to tie to (E) footing. Show (N) footing on plan
Sheet S2.1
EOR to clearly identify where is the new 7x PSL ridge beam ended, and how it is connected to 4x6. Clearly identify if two beams are at the same elevation
Sheet S4.0
Detail 10:
Provide strap tie and its spacing
Identify rafter size and spacing on plan under the California framing area
Prior to submit the hard-copy drawings for approval and permit issuance. It is at applicant’s discretion, as an option, to submit a full-set electronic drawing (in pdf format) for a courtesy review. Please include the original red-marked comment drawing set, red-marked calculation, and all supporting document (revised calculation, etc.) for an expedite review.
Red marked comment set is available to pick-up at the City Hall.(End of Comment)