PLAN CHECK NO:
101126352
PROJECT ADDRESS:
706 S Ross St
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/29/2026
INITIAL REVIEW
2/19/2026
EXPIRATION
7/28/2026
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Raz Grinbaum
3.
TEL:
(818)448-1355
FAX:
VALUATION: $80,000.00
EMAIL:
rgpermits1@gmail.com
FLOOD ZONE: X-06059C0276J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2025 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Applicant shall obtain clearance/approvals from following departments after obtaining approval from Building and Safety Division, prior to building permit issuance
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).
Applicant must pick up red marked sheet from the City prior to resubmittal and return the marked up set with resubmittal
PLAN REVIEW COMMENTS:
Sheet T-1
Insert the handwritten note in project data and scope of work into the typed note
All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service.
Provide the following design data on the first sheet (R106.1.1)
Automatic Fire Sprinkler (YES or NO)
Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.
For the purpose of Park & Rec Development fee calculation, please provide new ADU square footage to existing single family residence square footage ratio (ADU sf / SFD sf) on the Cover Sheet. Square footages shall NOT include garage, non-habitable attic space, non-habitable basement space, patio cover, patio enclosure, sunroom and similar uses.
Note on plan: The ADU sf / SFD sf ratio is for Park & Rec fee purpose only. The applicant is responsible for the given “SFR sf” of the existing primary residence; Building Safety staff are not responsible for the accuracy of the given “SFR sf”
Sheet A-1
Aging-in-place Design & Fall Prevention – (R327)
Reinforcement for grab bar: at least one bathroom on the entry level shall be provided with reinforcement installed. Where there is no bathroom on the entry level, at least one bathroom on the second or third floor of dwelling shall comply
Reinforcement shall be solid lumber or other construction materials approved by the enforcing agency.
Reinforcement shall not be less than 2x8 inches nominal lumber or other construction material provide equal height and load capacity. Reinforcement shall be located between 32 inches and 39 ¼ inches above the finished floor flush with the wall framing
Water closet reinforcement shall be install on both side walls of the fixture, or one side wall and the back wall
Shower reinforcement shall be continuous where wall framing is provided
Bathtub and combination bathtub/shower reinforcement shall be continuous on each end of the bathtub and the back wall. Additionally, back wall reinforcement for a lower grab bar shall be provided with the bottom edge located no more than 6 inches above the bathtub rim
Electrical receptacle outlet, switch and control height: Electrical receptacle outlets, switches and control (including controls for heating, ventilation and air conditioning) intended to be used by occupants shall be location no more than 48 inches measured from the top of the outlet box and not less than 15 inches measured form the bottom of the outlet box above the finish floor
Doorbell buttons: doorbell buttons or controls, when installed, shall not exceed 48 inches above exterior floor or landing, measured from the top of the doorbell button assembly. Where doorbell buttons integrated with other features are required to be installed above 48 inches measured from the exterior floor or landing, a standard doorbell button or control shall also be provided at a height not exceed 48 inches above exterior floor or landing, measure from the top of the doorbell button or controls.
Interior door: At least one bathroom and one bedroom on the entry level shall provide a door way with a net clear opening of not less than 32” measured with the door positioned at an angle of 90 degrees from the closed position. In the case of a two- or three-story single-family dwelling, on the second or third floor of the dwelling if a bathroom or bedroom is not located on the entry level.
Sheet A-2
Exterior wall covering – Detail corrosion–resistant weep screed minimum of 4” above the earth or 2” above paved areas. (R703.7.2.1)
Identify the maximum height of the parapet on the elevation plan
Identify/provide on plan the location of roof downspout
Roofing requirements – (R901)
A Class “C” roof is required. On the plan, specify manufacturer’s name, ICC/UL report number and Class for the roofing material.
Specify the pitch of the roof plan. Provide two layer of vapor barrier if roof slope is lower than 4:12.
Unvented attic and unvented enclosed rafter assembly shall comply ALL requirements with CRC section R806.5. Update detail 1/A-2 to reflect all requirements, including insulation, vapor retarder and etc.; otherwise, provide vented attic
Sheet S-1
Calculation provided was outdated under previous code cycle. Provide updated structural calculation for both gravity & lateral analysis under current code cycle of CBC 2025/ ASCE 7-22. Further review is required
Update design criteria/seismic coefficient on the plan per current code cycle of CBC 2025/ASCE 7-22
Sheet S-3
Detail 6: specify on plan the maximum parapet height (End of Comment)