HomeMy WebLinkAbout341207_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101127333
PROJECT ADDRESS:
2217 N Richmond St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/29/2026
INITIAL REVIEW
5/3/2026
EXPIRATION
10/26/2026
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Terry Booth
3.
TEL:
(714)981-5729
FAX:
VALUATION: $199,000.00
EMAIL:
Terry@newlandconstruction.com
FLOOD ZONE: X-06059C0164J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
The applicant shall obtain clearances/approvals for the following after obtaining approval from Building and Safety Division, prior to building permit issuance (CHECKED BOXES REQUIRED ONLY):
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. Applicant must pick up red marked sets from city prior to resubmittal and return marked up set with resubmittal.DrawingsSheet A-1
Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. The Building and Safety Division plan review does not include potential electrical, water, or gas revisions required by any non-city utility company. It is solely on the contractor to ensure proposed addition or alteration can and will meet utility company requirements. MEP are subject to building field inspection.Sheet California Green Building Standards CodeProvide sheet number on Green Code sheets.Applicant shall complete Green Code checklist.Sheet A-4
Show location(s) of 22" x 30" attic access with 30" minimum clear headroom. (R807.1) All doors and windows with direct access to pool shall be provided with an alarm unless approved alternative drowning prevention methods are specified on drawings.Sheet S1Verify specified holdown product with current manufacturer product list. Revise and redesign to current product listing.Verify sheet reference for detail 3/SD2 specified, detail does not look to be correct.Sheet S2Provide detail for ridge beam (bm1) to hip beam (hp1) connection.Identify size for shorter ridge beams on plan. All members shall be sized on plans unless clearly noted from another location.Provide detail for hip beam (hp3) to ridge beam (bm1) connection where shorter ridge beam occurs.Provide and verify RR framing and direction at far left area of new roof. It is unclear. Please verify existing lateral system along plan north side of existing house. There is concern what the resisting element is with so many openings. EOR to provide design for any new lateral system being used to resist existing as needed.Sheet SD3Detail 9 – Specify connection from existing to new beam and shear transfer as required for drag to new shearwall.CalculationsPage 2 of 18 – Add 2nd floor loading criteriaPage 7 of 18 – Justify ceiling rafter and ceiling beams to be fully braced. Page 13 of 18 – Verify if new ceiling beam is supporting SW above. Add SW loading with overstrength as required. Justify shear transfer from above to lateral system below. Shearwall along Gridline C shall be designed as a non-parallel system. Justify or redesign as needed. Verify if shearwall along Gridline 3 is used for resisting existing second story mass. Design as needed. (End of Comment)