HomeMy WebLinkAbout339351_3_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101126788
PROJECT ADDRESS:
2409 N Hesperian St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/9/2026
No Response letter submitted
INITIAL REVIEW
4/7/2026
EXPIRATION
9/5/2026
RECHECKS:
1.5/1/26
PROJECT APPLICANT CONTACT PERSON:
2.5/21/26
Raymundo Davila
3.
TEL:
(949)274-6469
FAX:
VALUATION: $35,000.00
EMAIL:
conejoconsturction8@gmail.com
FLOOD ZONE: X-06059C0144J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Provide a fully dimensioned Site Plan on the drawings .Ok 5/1/26Provide wall legend to distinguish between new / existing / demo walls.Ok 5/1/26Carbon monoxide alarms and smoke detector combined with smoke alarms shall comply with both sections R314 and section R315.Ok 5/1/26Show minimum headroom under new beam between kitchen and dining room.Ok 5/1/26Sheet A1-0, show new infills.Pending 5/1/26, Sheet A-1.3 show new infill.Sheet A-1.1, is toilet and lavatory being relocated.Ok 5/1/26Sheet A-1.1, not clear is there an opening between living room and kitchen is there a closet. Only entrance to the kitchen is from dining room?Ok 5/1/26Sheet A1.01, please verify if any shearwall is being removed by creating new opening.Pending 5/1/26, not found
Detail the shear transfer connections which transfer lateral forces from horizontal diaphragms through intermediate elements and shear walls to the foundation. (1603)Pending 5/1/26 , not found
Clearly identify all design assumptions & load criteria on the plans. As a minimum:Ok 5/1/26
- Dead Loads of roof/ceiling, floors, exterior/interior walls (R301.2.2.2.1);
- Live Loads for roof, attics with limited storage, attics without storage, habitable attics and attics
served with fixed stairs, floors, and balconies/decks, and stairs per Tables R301.5 & R301.6;
- Wind Loads per Section R301.2.1and wind exposures per Section R301.2.1.5;
- Seismic Loads per Section R301.2.2;
- Local Jurisdiction Design Criteria per Table R301.2(1)
On engineering calculation clearly identify loading on the new beam. Pending 5/1/26, show all loading including uniform loading from wall.
On engineering calculation show floor loading.Pending 5/1/26, not found
Sheet S1.01, is there any beam to support 2nd floor wall, show location of 2nd floor wall with regard to the first floor. Please see red mark.Ok 5/1/26
Sheet S1.10, detail 1/S1.00 provide minimum 12” deep footing.Ok 5/1/26
Sheet S1.10, scale of foundation plan and framing plan don’t match.Pending 5/1/26, still location of new post on foundation plan doesn’t match location on the floor plan.
Sheet S1.10, show location of new footing from 1/S100 with detail on section 1-1.Ok 5/1/26
Sheet S1.10, show 2-2x6, 2 ply doesn’t apply.Ok 5/1/26
Provide roof framing plan to show loading on the new beam.Pending 5/1/26, 2nd floor roof is flat? provide roof plan for first and 2nd floor roof.
Sheet S1.10, detail 3/ S1.10, floor joists direction doesn’t match floor framing 2/ S1.10.Pending 5/1/26, sheet S1.10 cross section 3 doesn’t apply to section detail.
Sheet S1.10, 2 ply doesn’t apply on header beam schedule show 2-2x6.Ok 5/1/26
5/1/26
Drawings shall be stamped and signed by Architect and engineer record.
Sheet S1.11, floor joists direction on framing detail 2, doesn’t match floor joists direction on 1st floor ceiling plan of sheet S1.10. Please clarify.
Clearly show tributary area and all applicable loading for new beam on calulation.