HomeMy WebLinkAbout331500_4_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101124361
PROJECT ADDRESS:
2414 N Tustin Ave
PLAN CHECK ENGINEER:
Lee, WayneTEL:714
647-5848
EMAIL:
wlee@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
7/16/2025
INITIAL REVIEW
8/5/2025
EXPIRATION
1/12/2026
RECHECKS:
1.10/06/2025
PROJECT APPLICANT CONTACT PERSON:
2.02/17/2026
Pete Gabrich
3.
TEL:
(949)622-8759
FAX:
(949)250-1529
VALUATION: $75,000.00
EMAIL:
Peterg@whainc.com
FLOOD ZONE: X-06059C0164J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)Final drawings and calculations shall be stamped and signed by the Registered Design Professional and shall include the date of signing below the stamp. (California Business & Professions Code 5537, 5538, 6737.1, and 6745).Sheet A0.00. Clarify the occupancy group within leasing office. Specify occupancy group per 2022 CBC Ch3. Plan shows occupancy group R-4 appears incorrect.Sheet A0.00. Indicate on the cover sheet that if the leasing office is equipped with fire-sprinkler system.Sheet A0.00. Show number of stories of the leasing office. Plan shows 2 and 3 story building is confusing and may not be correct.Sheet A0.00. Indicate total square footage of the tenant improvement area.Sheet A2.20. Detail 4/A3.00 shown in the wall legend is not available.Provide typical section view detail of all new partitions and ceilings showing:
- Size, spacing, and material of framing members
- Note gauge and ICC Research Report number and installation/construction requirements for metal framing
members.
- It is the project designer’s responsibility to coordinate work with the various trades to ensure that the size of
the wall cavity will be large enough to accommodate piping, fittings, ducts, etc. There has been a continuing
field problem of 2½” wide metal studs not being able to accommodate plumbing pipes.
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.16
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawing prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Provide on the drawings details for the lateral support of partitions, rails and similar space dividers less than
5’ 9” in height.
- Sheathing material and details of attachment. Note type, size, and spacing of fasteners.
- Heights of partition, suspended ceiling, structure above.
- Reference each fire-resistive assembly to a CBC Chapter 7 Table and Item number.
- Fire-blocks and draft-stops in combustible construction in accordance with CBC Section 718. Show
location(s) and provide typical construction details.
- Fire/smoke damper locations, installation requirements and required access doors. Refer to CBC Section 716
and mechanical Code Section 606.A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in Chapter 11B, 2022 CBC. Revise the drawings to show compliance. Provide details to show how existing non-compliant items will be upgraded to current standards.Building Division 3rd review comments: Not resolved. The provided site plan does not match current building record and on the site. The latest parking lot renovation was permitted under building permit number: 10197006 on 12/20/2018 and finaled. The submitted site plan appears to be outdated and does not reflect the current scope of work. Please provide an updated architectural site plan clearly indicating the required accessible path of travel improvements (if any) in accordance with applicable accessibility requirements. In addition, please clarify and revise the Disabled Access Compliance Form to accurately reflect the scope of accessible upgrades based on the project valuation of $75,000. Ensure consistency between the site plan and the compliance form.Show detailed information, including dimensions, on existing accessible parking, ramps, and toilet facilities, to verify conformance with the current requirements. (CBC 11B-502, 11B-405, 11B-603 through 11B-606.7)Building Division 3rd review comments: Pending to item #13.END OF COMMENTS