Detailed geometric studies, topographic surveys, and final construction <br />documents were prepared by Huitt-Zollars for this $5 million project to add one <br />through lane in each direction on Oso Parkway, right -turn -only lanes in each <br />direction on Marguerite Parkway, and create double left -turn lanes in all four <br />directions of the existing arterial highway intersection. Raised medians on all <br />four legs of the intersection were completely reconfigured. Design constraints <br />included access to existing developments, an adjacent hillside slope buttress, <br />major water pressure reducing station, and other utility vaults and facilities. This <br />project affected 4,600 linear feet of highway, three signalized intersections, and <br />included 1,700 linear feet of retaining walls. Construction plans, specifications, and estimates were prepared <br />for this $5 million project. The work of subconsultants for environmental documentation, traffic engineering, <br />landscape architecture, and cost estimating was coordinated by Huitt-Zollars. This project involved relocation of <br />numerous electrical, telephone, cable and gas utility facilities, and reinforcement of the underground vault for the <br />pressure reducing station. I � %IA „T ��1^ L, <br />CLIENT CONTACT: <br />City of Mission Viejo Public <br />Works <br />Mark Chagnon - Director <br />200 Civic Center Drive <br />Mission Viejo, CA 92691 <br />949.470.3091 <br />.......... <br />COMPONENETS: <br />Road Widening <br />Traffic Signals <br />Signage & Striping <br />Retaining Walls <br />Pavement Rehabilitation & <br />Overlay <br />Traffic Control/Construction <br />Huitt-Zollars was retained by Orange County Public Works to prepare <br />Letter of Design Recommendations (LODR) and final construction plans, <br />specifications and estimates for the improvement of the Oso Parkway / <br />Antonio Parkway intersection in South Orange County. The $2 million <br />project's purpose was to improve the capacity of this intersection to <br />accommodate increased traffic resulting from continued new residential <br />development throughout the region. Capacity improvements at the <br />intersection were as follows: <br />Antonio Parkway: Addition of a fourth southbound thru lane <br />and a third northbound left -turn lane onto Oso Parkway <br />Oso Parkway: Addition of a fourth eastbound thru lane <br />CLIENT CONTACT: <br />OC Public Works <br />Steve Soo - Project Manager <br />300 N. Flower Street <br />Santa Ana, CA 92703 <br />714.667.9659 <br />Right -of -Way <br />Storm Drain <br />Design, Geometrics & PS&E <br />Private PropertyAccess <br />Modifications <br />RELEVANT DESIGN <br />Traffic Control/Construction <br />COMPONENETS: <br />Phasing <br />Road Widening <br />Pavement Overlay/ <br />Traffic Signal <br />Rehabilitation <br />Signing & Striping <br />Design, Geometrics & <br />Right -of -Way <br />PS&E <br />HUITMJLLARS <br />City of Santa On -Call Water Resources Engineering Services RFP No. 19-100 12 <br />