Laserfiche WebLink
Page 8 of 53 <br />The milestones for completing the Project are: <br />Planned <br />Planned <br />Completion <br />Milestone / Task / Activity <br />Start Date <br />Date <br />Complete environmental and cultural compliance (note, <br />application says complete but there will be some <br />In process <br />September 2020 <br />Reclamation review at a minimum) <br />100% PS&E submittal & Approval <br />September <br />March 2021 <br />2020 <br />Installation of irrigation equipment <br />September <br />Dec 2020 <br />2020 <br />Public bid process <br />April 2021 <br />May 2021 <br />Award hydropower construction contract <br />June 2021 <br />July 2021 <br />Hydropower construction <br />August 2021 <br />July 2022 <br />Project completion <br />July 2022 <br />6. RESPONSIBILITY OF THE PARTIES <br />6.1 Recipient Responsibilities <br />6.1.1 The Recipient shall carry out the Scope of Work (SOW) in accordance with the terms and <br />conditions stated herein. The Recipient shall adhere to Federal, state, and local laws, regulations, <br />and codes, as applicable, and shall obtain all required approvals and permits. If the SOW <br />contains construction activities, the Recipient is responsible for construction inspection, <br />oversight, and acceptance. If applicable, the Recipient shall also coordinate and obtain approvals <br />from site owners and operators. <br />6.1.2. SA-1 Hydro -generator Federal Funds. Federal costs for the SA-1 hydro -generator in the <br />amount of $245,000.00 will be suspended in the ASAP payment system and shall not be <br />considered reimbursable until the Recipient has received a formal approval from the Grants <br />Officer as described in Section 6.1.3. <br />Agreement No. MOAP00077 Agreement Template <br />20 C -10 (03/2019) <br />