City of Santa Ana <br />Hydro Turbine Generators <br />Project Cost Estimate <br />SA-6 Install New Turbine Generator in a New Vault <br />Equipment Description <br />Gilkes 300 G100 Francis Turbine Assembly <br />Includes 300 G100 Francis Reaction Turbine, Case, Runner, Bearing Housing, Guide Vanes <br />and Linkages, Inlet Spool Pipe, Outlet Bend and Draft, Tube, Shims, Main Inlet Valve, <br />Induction Generator, Controls & Switchgear Package, Hydraulic Power Unit. <br />Commisioning Parts, Startup, Site Testing <br />Vault- Excavation, concrete, backfill, lid, sidewalk, landscaping <br />10, x 10, at $350/sf <br />Mechanical/Electrical Building Modifications <br />Construction, EPC Contractor <br />Demolition of Existing Plant (Offsetting with Salvage Value) <br />Salvage Value of Existing In Line Turbine <br />Shipping - In Line Turbine <br />Development Costs - Permitting, Interconnection, SCE <br />Balance of Plant Contingency <br />Subtotal <br />Materials + Labor <br />Sales Tax on Materials <br />Contractor Construction Management <br />Contractor O&P <br />Contingency on Construction Contract <br />Design Engineering <br />City Project Management <br />City Construction Support <br />Project Total <br />References <br />1. Canyon Hydra Proposal 17 Aug 2018 <br />2. NAM <br />Extended Bare Bare Labor Extended <br />Bare Material Material Cost Cost per Unit Bare Labor <br />Qty Cost Per Unit ($) ($) ($) Costs ($) Reference <br />1 $ 398,919 $ 398,919 $ $ 1 <br />0 $ <br />- <br />$ - <br />$ - 1 <br />1 <br />$ - <br />$ 10,000 <br />$ 10,000 1 <br />1 $ <br />15,000 <br />$ 15,000 <br />$ 20,000 <br />$ 20,000 <br />0 $ <br />$ <br />$ <br />0 $ <br />$ - <br />$ - 2 <br />1 $ <br />10,000 <br />$ 10,000 <br />$ 10,000 <br />$ 10,000 2 <br />1 $ <br />$ - <br />$ 100,000 <br />$ 100,000 2 <br />1 $ <br />$ <br />$ <br />$ <br />1 $ <br />$ - <br />$ - <br />$ - <br />1 $ <br />5,000 <br />$ 5,000 <br />$ 2 <br />1 <br />$ <br />$ <br />1 $ <br />35,000 <br />$ 35,000 <br />$ 5,000 <br />$ 5,000 2 <br />1 <br />$ <br />$ <br />1 $ <br />25,000 <br />$ 25,000 <br />$ - 2 <br />$ 488,919 <br />$ 145,000 <br />$ 633,919 <br />9.2S% <br />$ 45,225 <br />S% <br />$ 31,696 <br />15% <br />$ 95,088 <br />20% <br />$ 126,784 <br />9% <br />$ 57,053 <br />7% <br />$ 44,374 <br />6% <br />$ 38,035 <br />$ 1,072,174 <br />City Council <br />26 - 165 <br />12/7/2021 <br />PREVIEW Date: Nov 03, 2021 Workspace ID: WS00800354 Funding Opportunity Number: R22AS00023 <br />