CITY OF SANTA ANA <br />PUBLIC WORKS AGENCY <br />CONTRACT CHANGE ORDER <br />Date: July 11, 2023 <br />19-6438, 19-6439,19-6440 <br />Project Number SR-55/Ritchey Water Main Improvements Change Order Number 002 <br />To James W Fowler Co. <br />Contractor <br />You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br />specifications on this contract. <br />NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTILAPPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br />Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br />Change requested by PUBLIC WORKS AGENCY <br />EXTRA WORK AT AGREED PRICE <br />Change Order 2 — Line Item <br />QTY <br />Unit <br />Unit Price <br />Total Amount <br />Time <br />RFQ-002, PCO-002 Additional MCI <br />1 <br />FA <br />$5,500.00 <br />$5,500.00 <br />TBD Days <br />Potholing as Directed by the Engineer <br />RFQ-002, PCO-003 Additional Utility <br />Potholing as Directed by the Engineer <br />1 <br />FA <br />$17,000.00 <br />$17,000.00 <br />TBD Days <br />PCO-010 Obstruction — Remove and <br />Dispose Thick Asphalt Concrete <br />Pavement and Concrete Slabs under <br />1 <br />FA <br />$45,000.00 <br />$45,000.00 <br />TBD Days <br />Existing Asphalt Concrete Pavement at <br />Various Locations on Ritchey St <br />TOTAL COST <br />$67,500.00 <br />TBD Days <br />Payment for the three line items is estimated and is to be Force Account per General Provisions 3-3.2.1. <br />Time impacts, if any, are to be determined (TBD). The Contractor reserves the right to submit a sub -network <br />analysis in compliance with Technical Specifications Section 01310. Construction Schedule, F, Change <br />Orders, for review and approval by the City of Santa Ana. <br />Page 1 of 2 <br />