Laserfiche WebLink
3.0 Construction Detail <br />Construction Phase <br />Phase <br />Number <br />Phase Name Phase Type Start Date End Date Num Days <br />Week <br />Num Days Phase Description <br />1 Demolition Demolition 5/12/2022 6/17/2022 5 27 <br />2 Grading Grading 6/18/2022 6/24/2022 5 5 <br />3 Building Construction Building Construction 6/25/2022 7/9/2023 5 270 <br />4 Paving Paving 7/10/2023 7/27/2023 5 14 <br />5 Architectural Coating Architectural Coating 7/28/2023 8/16/2023 5 14 <br />OffRoad Equipment <br />Phase Name Offroad Equipment Type Amount Usage Hours Horse Power Load Factor <br />Architectural Coating Air Compressors 1 6.00 78 0.48 <br />Paving Cement and Mortar Mixers 1 6.00 9 0.56 <br />Demolition Concrete/Industrial Saws 1 8.00 81 0.73 <br />Building Construction Cranes 1 6.00 231 0.29 <br />Building Construction Forklifts 1 6.00 89 0.20 <br />Building Construction Generator Sets 1 8.00 84 0.74 <br />ROG NOx CO SO2 Fugitive <br />PM10 <br />Exhaust <br />PM10 <br />PM10 <br />Total <br />Fugitive <br />PM2.5 <br />Exhaust <br />PM2.5 <br />PM2.5 <br />Total <br />Bio- CO2 NBio-CO2 Total CO2 CH4 N20 CO2e <br />Percent <br />Reduction <br />6.66 19.64 27.61 37.31 48.02 6.06 46.18 48.02 5.69 41.86 0.00 31.53 31.53 28.59 30.85 31.52 <br />Residential Indoor: 148,838; Residential Outdoor: 49,613; Non-Residential Indoor: 0; Non-Residential Outdoor: 0; Striped Parking Area: 1,748 <br />(Architectural Coating – sqft) <br />Acres of Grading (Site Preparation Phase): 0 <br />Acres of Grading (Grading Phase): 5 <br />Acres of Paving: 0.67 <br />CalEEMod Version: CalEEMod.2020.4.0 Date: 11/10/2021 12:49 PMPage 7 of 27 <br />19386 Cabrillo at First Mixed-Use Residential - Orange County, Summer <br />EMFAC Off-Model Adjustment Factors for Gasoline Light Duty Vehicle to Account for the SAFE Vehicle Rule Applied <br />Apx-11 <br />6/27/2022 <br />Planning Commission 2 –171