3. This Change Order Number 008, Item C provides additional compensation to Contractor for <br /> storage of Sound Panels at the manufacture's facilities as described in COR#31 —Acoustic Panel <br /> Storage 2.0. All labor, materials, and equipment necessary to store the Sound Panels are <br /> included in this Change Order Number 008, Item C. <br /> Work to be paid at agreed price in accordance with Section 7-3.7- "Agreed Price" of the Standard <br /> Specifications for Public Works Construction. <br /> The total cost of Change Order Number 008, Item C is four thousand, four hundred forty-eight <br /> and 44/100 dollars ($4,448.44). This sum constitutes full and complete compensation for <br /> furnishing all labor, materials, equipment, tools, transport, and incidentals including all markups <br /> by reason of this Change Order 008, Item C. Zero (0) working days are added as part of this <br /> Change Order 008, Item C. <br /> CHANGE ORDER NUMBER 008, ITEM C COST: $4,448.44 <br /> 4. This Change Order Number 008, Item D provides additional compensation to Contractor for all <br /> items as described in COR#33—Combination of Extra Work which includes T&M concerning Bio <br /> Swale Additional Excavation, Installing Driveways Extra Sleeves, and removal and abandonment <br /> of Unidentified Pipe. <br /> Work to be paid at agreed price in accordance with Section 7-3.7-"Agreed Price" of the Standard <br /> Specifications for Public Works Construction. <br /> The total cost of Change Order Number 008, Item D is fourteen thousand, nine hundred eighty- <br /> four and 621100 dollars ($14,984.62). This sum constitutes full and complete compensation for <br /> furnishing all labor, materials, equipment, tools, transport, and incidentals including all markups <br /> by reason of this Change Order 008, Item D. Four (4) working days are added as part of this <br /> Change Order 008, Item D. <br /> CHANGE ORDER NUMBER 008, ITEM D COST: $14,984.62 <br /> Page 2 of 4 <br />