Construction Contract Award: SR-55/Ritchey Street Water Improvements
<br />December 21, 2021
<br />Page 3
<br />2
<br />3
<br />4
<br />2
<br />of the Contractor’s work to ensure contract compliance, workmanship, and quality; and
<br />materials testing. As indicated in the Cost Analysis (Exhibit 4) and as summarized in the
<br />table below, the estimated total construction delivery cost of the project is $7,250,000.
<br />Project Item Total
<br />Construction Contract $5,922,025
<br />Construction Administration, Inspection, Testing $180,000
<br />Contingencies $997,975
<br />Water Engineering $150,000
<br />TOTAL CONSTRUCTION DELIVERY COST $7,250,000
<br />On May 5, 2020, the City Council authorized execution of three utility reimbursement
<br />agreements (Exhibits 5, 6, and 7) with OCTA for water relocation costs related to the SR-
<br />55 freeway widening project. The sum of the three utility agreements totals $6,600,000,
<br />with an allowable final billing of 125 percent, for a total estimated reimbursement of
<br />$8,250,000. On November 2, 2021, the City Council approved an appropriation
<br />adjustment to recognize $1,000,000 in reimbursement obligation funds. To account for
<br />the full 125 percent reimbursement allowable, the recommended action will recognize the
<br />remaining available balance. Therefore, staff recommends appropriating $7,250,000 of
<br />these reimbursement obligation funds from OCTA to complete the funding for
<br />construction of the SR-55/Ritchey Street Water Improvements Project.
<br />ENVIRONMENTAL IMPACT
<br />In accordance with the California Environmental Quality Act, the recommended actions
<br />are exempt from further review.
<br />FISCAL IMPACT
<br />Approval of the requested Appropriation Adjustments will recognize $7,250,000 in
<br />reimbursement obligation funds from OCTA, as outlined in the Cooperative Agreement
<br />No. C-0-2201 and three Utility Reimbursement Agreements for the State Route 55
<br />Improvement Project, into the Acquisition & Construction, Water Utility Capital Projects,
<br />Expense Reimbursement-OCTA revenue account (No. 06617647-57004) and
<br />appropriate the same amount into the Acquisition & Construction, Water Utility Capital
<br />Projects, Water Capital Project expenditure account (No. 06617647-66301).
<br />All funds expended for the water relocation project costs are anticipated to be reimbursed
<br />by the Orange County Transportation Authority (OCTA). Funds will be budgeted and
<br />available for expenditure in Account No. 06617647-66301 in the following water relocation
<br />projects: $2,520,000 for Project No. 19-6438, $2,530,000 for Project No. 19-6439, and
<br />$2,200,000 for Project No. 19-6440.
<br />The following table summarizes the funds budgeted and available for expenditure to
<br />deliver construction of this project. Any remaining balances not expended at the end of
<br />the fiscal year will be carried forward for expenditure in the following fiscal year.
|