Laserfiche WebLink
ID Task <br />Mode <br />Task Name Duration Start Finish Predecessors <br />1 <br />2 Santa Ana Zoo Video <br />Surveillance Project <br />3 <br />4 Notice of Award 1 day Wed 4/21/21 Wed 4/21/21 <br />5 Kick off Meeting 1 day Thu 4/22/21 Thu 4/22/21 <br />6 Delivery of Submittals 1 day Fri 4/23/21 Fri 4/23/21 5 <br />7 Review and Approval of Submittals 2 days Mon 4/26/21 Tue 4/27/21 6 <br />8 Owner to provide IP Schemes for <br />all locations <br />1 day Mon 4/26/21 Mon 4/26/21 <br />9 Procurement of Equipment 5 days Wed 4/28/21 Tue 5/4/21 7 <br />10 Programming of all Equipment 3 days Wed 5/5/21 Fri 5/7/21 9 <br />11 Delivery of equipment to site 1 day Mon 5/10/21 Mon 5/10/21 10 <br />12 Notice to Proceed 1 day Mon 5/10/21 Mon 5/10/21 <br />13 <br />14 CONSTRUCTION ACTIVITIES - <br />Install of switch cameras & <br />15 Initial survey of site conditions & <br />mobilization <br />1 day Tue 5/11/21 Tue 5/11/21 12 <br />16 Installation of Server ( Video <br />Recorder) <br />1 day Wed 5/12/21 Wed 5/12/21 15 <br />17 Installation of cables, conduit and <br />antennas <br />6 days Thu 5/13/21 Thu 5/20/21 16 <br />City <br />ALL <br />Edgeworth <br />City <br />City <br />Edgeworth <br />Edgeworth <br />Edgeworth <br />City <br />Edgeworth <br />Edgeworth <br />Edgeworth <br />O N D J F M A M J J A S <br />Half 1, 2021 Half 2, 2021 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Progress <br />Manual Progress <br />Page 1 <br />Project: Santa Ana Zoo Video S <br />Date: Mon 4/5/21