Ali Pezeshkpour, Planning Manager <br />Page 2 <br />Project Timeline <br />This letter presents the Project's permitting history in three distinct phases, punctuated <br />by key milestones, to present the information in the clearest way possible. <br />Phase 1: Application Submittal to Application Completeness Determination <br />On November 10, 2021, the applicant submitted the full development application. <br />Under the Permit Streamlining Act, local governments have 30 calendar days after the <br />development application submittal to inform the applicant of whether the application is <br />complete. If the local government does not inform the applicant of any deficiencies <br />within that 30-day period, the application will be "deemed complete," even if it is <br />deficient (Gov. Code, § 65943, subd. (a )).2 <br />The City failed to inform the applicant in writing that the application was not complete <br />by December 10, 2021 (i.e., 30 days from the date of submittal). Therefore, on <br />December 10, 2021, the application was deemed complete by operation of law. <br />Phase 2: Application Completeness Determination to Project Consistency <br />Determination <br />The HAA requires that for housing development projects containing 150 or fewer <br />housing units, the local agency has 30 days from the date the development application <br />is deemed complete to provide the applicant with written documentation of any <br />inconsistency, incompliance, or inconformity with the applicable plan, program, policy, <br />ordinance, standard, requirement, or other similar provision (Gov. Code, § 65589.5, <br />subd. 0)(2)(A)(i)). If the local agency does not provide written documentation of such <br />findings within 30 days, the development project shall be deemed consistent, <br />compliant, and in conformity of the applicable plan, ordinance, and standards (Gov. <br />Code, § 65589.5, subd. (j)(2)(13)). <br />The City failed to inform the applicant in writing of any inconsistencies by January 9, <br />2022 (i.e., 30 days from the date that the application was deemed complete by <br />operation of law). Therefore, on January 9, 2022, the Project was deemed consistent <br />and compliant with the applicable plan, ordinance, and standards by operation of law. <br />On the same date, the Project became vested under the HAA (Gov. Code, § 65589.5, <br />subd. (j)(1)). Note that the Project's vesting is not based on the submittal of a <br />Preliminary Application (Gov. Code, § 65941.1) because the applicant did not submit a <br />Preliminary Application. The Project's vesting occurred when the application was <br />deemed consistent by operation of law (Gov. Code, § 65589.5, subd. (h)(5)). <br />2 See also Housing Accountability Act Technical Assistance Advisory Memo, dated <br />September 15, 2020, Page 8. <br />