<br />2023 M2 Regional Capacity Program Call for Projects -
<br />Programming Recommendations
<br />Agency
<br />Fiscal
<br />Year Project Fund Phase
<br /> M2 Funding
<br />Engineering
<br /> M2 Funding
<br />Right-of-Way
<br /> M2 Funding
<br />Construction* Total M2 Funding Match Totals
<br /> Match
<br />Rate
<br />Irvine 24/25 Jamboree Road and Main Street Intersection
<br />Enhancements ICE CON 1,414,124$ 1,414,124$ 471,374$ 1,885,499$ 25%
<br />Santa Ana 23/24 Bristol Street and Memory Lane Intersection
<br />Improvements1 ICE CON 1,501,900$ 1,501,900$ 500,740$ 2,002,640$ 25%
<br />Santa Ana 23/24 Bristol Street Improvements Phase 3A -
<br />Civic Center Drive to Washington Avenue1 ACE CON 5,239,044$ 5,239,044$ 1,746,681$ 6,985,725$ 25%2
<br />Santa Ana 23/24 Bristol Street Improvements Phase IV -
<br />Warner Avenue to Saint Andrew Place1 ACE CON 11,910,061$ 11,910,061$ 3,970,354$ 15,880,415$ 25%2
<br />Santa Ana 23/24 Warner Avenue Improvements -
<br />Oak Street to Grand Avenue1 ACE CON 11,997,206$ 11,997,206$ 3,999,069$ 15,996,275$ 25%
<br />Yorba Linda 23/24 Lakeview Avenue Improvements from
<br />Lemon Drive to Oriente Drive ACE ENG 331,875$ 331,875$ 110,625$ 442,500$ 25%
<br />Yorba Linda 23/24 Lakeview Avenue Improvements from
<br />Bastanchury Road to Oriente Drive1 ACE CON 1,083,259$ 1,083,259$ 361,086$ 1,444,345$ 25%
<br />331,875$ -$ 33,145,594$ 33,477,469$ 11,159,929$ 44,637,399$
<br />1 Reapplication project from prior cycles.
<br />2 The original match rate unintentionally included ineligible costs and has been corrected.
<br />*Includes escalation of 4.9% for all construction projects programmed for fiscal year 2024/25.
<br />UNFUNDED (Project withdrawn by applicant)
<br />Agency
<br />Fiscal
<br />Year Project Fund Phase
<br /> M2 Funding -
<br />Engineering
<br /> M2 Funding -
<br />Right-of-Way
<br /> M2 Funding -
<br />Construction Total M2 Funding Match Totals
<br /> Match
<br />Rate
<br />Anaheim 23/24 Lincoln Avenue Improvements (East Street to
<br />Evergreen Street)ACE CON 6,905,415$ 6,905,415$ 2,301,805$ 9,207,220$ 25%
<br />County of Orange 23/24 Cow Camp Road Segment 2C-2.A Construction ACE CON 5,853,825$ 5,853,825$ 5,853,825$ 11,707,650$ 50%
<br />Acronyms:
<br />ACE - Arterial Capacity Enhancements
<br />CON - Construction
<br />ENG - Engineering
<br />ICE - Intersection Capacity Enhancements
<br />M2 - Measure M2
<br />PROGRAMMING TOTALS
|