Laserfiche WebLink
TOTAL <br />TASKS June July August Sept. Oct. Nov. Dec. Jan. Feb. March April May June July August Sept. Oct. Nov. Dec. Jan. Feb. Mar.HOURS <br />1 CONSTRUCTABILITY REVIEWS <br />Constructability Review - 60% Design Documents <br />Document Review X X <br />Meetings/Site Visits X <br />Peer Estimate X <br />Constructability Review, including VE Session X <br />Project Executive: 40 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 80 <br />Construction Manager:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Inspector: 8 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Safety Officer:0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 <br />Constructability Review - 90% Construction Documents <br />Document Review X X X <br />Meetings/Site Visits X X <br />Peer Estimate X X <br />Constructability Review, including VE Session X X <br />Develop Project Schedule X <br />Develop Site Utilization Plan X <br />Project Executive:0 0 40 40 40 32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 152 <br />Construction Manager:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Inspector:0 0 8 8 16 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24 <br />Estimator:0 0 0 0 32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 32 <br />Safety Officer:0 0 0 0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 <br />Develop Contractor Pre-Qualification Process X <br />Project Executive:0 0 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Construction Manager:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Inspector:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />2 CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES <br />Bid Process <br />Prepare Bid Packages X <br />Pre-Bid Meeting X <br />Bid Analysis and Recommendations X <br />Permitting X <br />Project Executive:0 0 0 0 0 0 32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 32 <br />Construction Manager:0 0 0 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Project Inspector:0 0 0 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Preconstruction <br />PreCon Meeting X <br />Collect GC Insurance, New Vendor Packet, etc. X <br />Project Executive:0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 20 <br />Construction Manager:0 0 0 0 0 0 0 40 0 0 0 0 0 0 0 0 0 0 0 0 0 40 <br />Project Inspector:0 0 0 0 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Project Administrator:0 0 0 0 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 16 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Construction - CM Services <br />Budget Management X X X X X X X X X X X X X X <br />Schedule Management X X X X X X X X X X X X X X <br />Submittal Process X X X X X X X X X X X X X X <br />RFI Process X X X X X X X X X X X X X X <br />Change Management Process X X X X X X X X X X X X X X <br />Pay Application Review Process X X X X X X X X X X X X X X <br />Monitor Prevailing Wage Process X X X X X X X X X X X X X X <br />Meetings X X X X X X X X X X X X X X <br />Project Executive:0 0 0 0 0 0 0 0 10 10 10 10 10 10 10 10 10 10 10 10 10 10 140 <br />Construction Manager:0 0 0 0 0 0 0 0 100 100 100 100 100 100 100 100 100 100 100 100 100 100 1400 <br />Project Inspector:0 0 0 0 0 0 0 0 16 16 16 16 16 16 16 16 16 16 16 16 16 16 224 <br />Project Administrator:0 0 0 0 0 0 0 0 80 80 80 80 80 80 80 80 80 80 80 80 80 64 1104 <br />Scheduler:0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 28 <br />Estimator:0 0 0 0 0 0 0 0 4 4 4 4 4 4 4 4 4 4 4 4 4 4 56 <br />Safety Officer:0 0 0 0 0 0 0 0 8 8 8 8 8 8 8 8 8 8 8 8 8 8 112 <br />Construction - Inspection Services <br />Daily Inspections X X X X X X X X X X X X X X <br />Coordinate Special & Material Inspections X X X X X X X X X X X X X X <br />Produce Daily Job Log X X X X X X X X X X X X X X <br />Monitor GC's Safety Program X X X X X X X X X X X X X X <br />Project Executive:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Construction Manager:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Inspector:0 0 0 0 0 0 0 0 128 128 128 128 128 128 128 128 128 128 128 128 128 128 1792 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Reporting and Communication <br />Prepare Weekly Statement of Working Days X X X X X X X X X X X X X X <br />Prepare Monthly Report X X X X X X X X X X X X X X <br />Project Executive:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Construction Manager:0 0 0 0 0 0 0 0 8 8 8 8 8 8 8 8 8 8 8 8 8 8 112 <br />Project Inspector:0 0 0 0 0 0 0 0 16 16 16 16 16 16 16 16 16 16 16 16 16 16 224 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Project Close-Out <br />Prepare and Manage Punchlist Process X <br />Assemble Close-out Documuments, including all as-built and record drawings X <br />Manage Commissioning Process X <br />Arrange for Final Inspections and Process Paperwork X <br />Project Executive:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Construction Manager:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 32 32 <br />Project Inspector:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 8 <br />Project Administrator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 16 <br />Scheduler:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Estimator:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />Safety Officer:0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 <br />We have based our schedule and pricing on the following milestones/durations <br />1. Desing Phase completion of six (6) months <br />2. Bid Process of one (1) month <br />3. Preconstruction phase of one (1) month <br />4. Construction Phase of fourteen (14) months, including close-out <br />Additioanlly, hours and cost distribution are approxiamte only and provided for accounting purposes. <br />TASKS <br />Hrs Rate $$ Hrs Rate $$ Hrs Rate $$ Hrs Rate $$ Hrs Rate $$ Hrs Rate $$ Hrs Rate $$ <br />1 CONSTRUCTABILITY REVIEWS $84,936 <br />Constructability Review - 60% Design Documents 80 251 $20,080 165 $0 24 115 $2,760 125 $0 153 $0 16 197 $3,152 4 160 $640 $26,632 <br />Constructability Review - 90% Construction Documents 152 251 $38,152 165 $0 48 115 $5,520 125 $0 24 153 $3,672 32 197 $6,304 4 160 $640 $54,288 <br />Develop Contractor Pre-Qualification Process 16 251 $4,016 165 $0 115 $0 125 $0 153 $0 197 $0 160 $0 $4,016 <br />2 CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES $749,628 <br />Bid Process 32 251 $8,032 16 165 $2,640 16 115 $1,840 125 $0 153 $0 197 $0 160 $0 $12,512 <br />Preconstruction 20 251 $5,020 40 165 $6,600 16 115 $1,840 16 125 $2,000 153 $0 197 $0 160 $0 $15,460 <br />Construction - CM Services 140 251 $35,140 1400 165 $231,000 224 115 $25,760 1104 125 $138,000 28 153 $4,284 56 197 $11,032 112 160 $17,920 $463,136 <br />Construction - Inspection Services 251 $0 165 $0 1792 115 $206,080 125 $0 153 $0 197 $0 160 $0 $206,080 <br />Reporting and Communication 251 $0 112 165 $18,480 224 115 $25,760 125 $0 153 $0 197 $0 160 $0 $44,240 <br />Project Close-Out 251 $0 32 165 $5,280 8 115 $920 16 125 $2,000 153 $0 197 $0 160 $0 $8,200 <br />SUBTOTAL $834,564 <br />CONSTRUCTION CONTINGENCY @ 20%$166,913 <br />TOTAL FEE $1,001,477 <br />Constr. Manager Subtotals <br />CITY OF SANTA ANA - RFP: CONSTRUCTION MANAGEMENT SERVICES FOR AQUATIC CENTER AT MEMORIAL PARK <br />Schedule / Estimated Hours per Task <br />2024 2025 2026 <br />Safety Manager <br />CITY OF SANTA ANA - RFP: CONSTRUCTION MANAGEMENT SERVICES FOR AQUATIC CENTER AT MEMORIAL PARK <br />FEE PROPOSAL <br />Project Executive Project Inspector Admin. Manager Scheduler Estimator <br />  <br />  <br />City Council 28 – 26 6/4/2024