CITY OF SANTA ANA <br /> .r PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> Project Number Project No. 20-6965:STANDARD-MCFADDEN BIKEWAY Change Order Number 3 <br /> IMPROVEMENTS <br /> To Vido Samarzich, Inc Contractor <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE:THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actualiy used and no allowance will be made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> EXTRA WORK AT AGREED PRICE <br /> 1. Modification of signage and striping along Standard Ave. including addition of nine (9) signs, <br /> removal of four (4) signs, and Detail 39A striping per PCO #21 dated September 16, 2025. <br /> AGREED PRICE = $4,432.89 <br /> 2. Reroute of utility conduit in conflict with Pole 5 at the Standard-Shelton intersection per PCO#22 <br /> dated September 24, 2025. <br /> AGREED PRICE = $10,512.54 <br /> 3. Install of driveway at 816 E. Chestnut Ave. not included in original Contract scope per PCO #18 <br /> dated October 23, 2025. <br /> AGREED PRICE = $3,500.00 <br /> 4. Install of St. Augustine sod, ADA ramp, striping and sidewalk at 1653 McFadden not included in <br /> Contract scope per PCO #23 dated November 13, 2025. <br /> AGREED PRICE = $1,878.15 <br /> 5. Install of ADA ramp including mobilization, trucking, saw cutting, and short load fees per PCO <br /> #24 dated December 16, 2025. <br /> AGREED PRICE = $5,500.00 <br /> Page 1 of 3 <br />