6. To compensate the contractor for demolition and rebuild scope adjustment— Framing & MEP <br /> per ASI-0020 & CRX-0021.1. <br /> TOTAL AGREED PRIG = $712,601.62 <br /> 7. To compensate the contractor for marble finish changes per RFI-0105 & CRX-0031. <br /> TOTAL AGREED PRICE=$3,464.10 <br /> 8. To compensate the contractor for wall strengthening steel field modifications per RFI-0086 & <br /> CRX-0037. <br /> TOTAL AGREED PRICE=$4,382.90 <br /> 9. To compensate the contractor for the controls specification update per RFI-0080 & CRX- <br /> 0038. <br /> TOTAL AGREED PRICE =$11,259.69 <br /> 10.To compensate the contractor for the coordination study— breaker change per Submittal-26- <br /> 0573 & CRX-0023. <br /> TOTAL AGREED PRICE = $2,383.24 <br /> 11.To compensate the contractor for the basement concrete demolition for plumbing per CRX- <br /> 0063. <br /> TOTAL AGREED PRICE =$83,460.56 <br /> TOTAL AGREED INCREASE = $836,354.30 <br /> TOTAL AGREED CONTRACT CHANGE ORDER COST= $601218.18 <br /> Page 2 of 3 <br />