Laserfiche WebLink
8. To cover the costs of added floor drains per Bulletin #09, (PCO #032). <br /> AGREED Cosy: $ 27,484.90 <br /> 9. To cover the cost for Line Up support truck for SCE Power Pole. (PCO #036) <br /> AGREED COST: $7,303.24 <br /> 10. To cover the cost of painting exterior signage. (PCO#034) <br /> AGREED COST: $2,227.50 <br /> 11. To cover the cost of structural observation report adjustments per RFI#152. (PCO#038) <br /> AGREED COST: $2,447.81 <br /> 12. To cover the cost for Bulletin #8 and RFI #096 response (PCO#030) <br /> AGREED COST: $ 12,965.17 <br /> 13. To cover the cost for the emergency stop switch per RFI #121.2 response (PCO#039) <br /> AGREED COST: $ 3,944.94 <br /> TOTAL AGREED COST: $90,043.55 <br /> NET CONTRACT INCREASE : $37,866.66 <br /> Page 2 of 3 <br />