CITY OF SANTA ANA <br /> 0,.. <br /> PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> 1 04 <br /> Project Number Project No. 24-6045 Traffic Signal Installation at Segerstrom Change Order Number 1 <br /> Avenue and Spruce Street <br /> To Elecnor Belco Electric, Inc. Contractor <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE:THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> The compensation both time and cost set forth in this change order comprises the total compensation due the <br /> Contractor, all Subcontractors, and all Suppliers for all work performed per this change order, including impact on <br /> unchanged work. By signing this change order, the Contractor acknowledges and agrees on behalf of himself, all <br /> Subcontractors, and all Suppliers, that the stipulated compensation includes payment for all work contained in this <br /> change order, plus all payment for interruption of schedules, extended field overhead, home office overhead, profit, <br /> delay, and all impact, ripple effect or cumulative impact on all other work under this change order. The signing of <br /> this change order constitutes full mutual accord and satisfaction for all changes and work performed on this change <br /> order, and that the time and cost paid per this change order constitutes the total equitable adjustments owed the <br /> Contractor, all Subcontractors, and all Suppliers for all work performed on this change order. The Contractor on <br /> behalf of himself, all Subcontractors, and all Suppliers agrees to waive all rights, without exception or reservation <br /> of any whatsoever to file any further claim related to this change order. <br /> TOTAL COST THIS CHANGE ORDER: DECREASE $ _______________ INCREASE $ 51,880.57 <br /> By reason of this order the CONTRACT TIME completion will be adjusted as follows: Ten (10)Working Days <br /> We the undersigned contractor have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide <br /> all equipment,furnish all materials,except as may otherwise be noted above,and perform all service necessary for the work above specified,and will accept <br /> as full payment therefor the prices shown above. <br /> Accepted,Date 5/14/26 Contractor Elecnor Belco Electric, Inc. <br /> By P Title Pablo Sanchez, Chief Operating Officer <br /> Approval recommended b Date U ZC <br /> RUBL WORf� AG NC C VE DIRECTOR <br /> WIDUApproved by � Date p <br /> CITY MANAGER <br /> Attest: `` J Date <br /> ITY CLERK <br /> Page 2 of 2 <br />