Santa Ana Bridge Rehabilitation and Bike Trail Structure 12/27/2004 <br />components of the structural improvements for the proposed bridge widening and <br />reconstruction. <br />1. All plans will be prepared in English units. <br />2. Seismic analysis will follow the procedures as outlined in Caltrans SDC and <br />chapter 20 of the Caltrans Memo to Designers. Effect of the combined structures <br />will be analyzed, and additional retrofit requirement in addition to the bridge <br />widening will be evaluated. <br />3. Structural aesthetics design will be included for the design of the structure barrier <br />rails on Flower Street. Bridge aesthetics will follow the treatment on the existing <br />structure. <br />4. Bridge structures will be designed following the latest Caltrans Seismic Design <br />Criteria (SDC). <br />5. Because the bridge widening would involve a partial removal of the existing <br />bridge overhang, the widening will be designed with the properly coordinated <br />construction sequence and staging plans. Construction joints will be placed and <br />specified on the plans to indicate location of splices. <br />6. Utility list will be updated at the bridge. New utility openings will be provided to <br />accommodate new or realigned utilities. Utility relocation will be referenced in the <br />bridge plans. <br />7. Bridge railings will be designed in accordance to the FHWA memorandum on <br />Bridge Rail Analysis shown in exhibit 6-F of the Local Assistance Program <br />Guidelines. <br />The Unchecked Details plans and specifications will be submitted to the City of Santa <br />Ana and Caltrans. It has been our experience that Caltrans will review the unchecked <br />details plans (65% plans), but the railroad companies, US Corps of Engineers, County of <br />Orange Flood Control District and Orange County Harbor Beaches and Parks, will not <br />review them until the plans are near complete. The 65% plans will thus not be submitted <br />to these agencies. <br />DELIVERABLES: PRELIMINARY ESTIMATES <br />DRAFT STRUCTURE SPECIAL PROVISIONS <br />65% UNCHECKED DETAIL PLANS. <br />TASK 5 - 90% PS&E CHECKED DETAILS <br />The WKA Team will follow the Caltrans practice and the plans will be checked <br />independently by a registered engineer. The intent is to swap between the designers <br />and checkers in order to maintain objectivity of the independent checking process. <br />Differences in the calculations will be reconciled first before the Initial Plans will be <br />submitted to Caltrans for review and approval. <br />WKA will prepare a final quantity takeoff based on the standard Item List developed in <br />accordance with the Caltrans Standard Specification and SSP. Designer quantity take- <br />offs will be compared with the independent quantity takeoffs following the completion of <br />unchecked Details Plans. We will also prepare a complete set of independent quantity <br />check calculations of all structural components. The quantities will be compared with the <br />designers quantity takeoffs, and all structure bid items will be checked in accordance <br />with Caltrans Bridge Design Aids Section 11 "Estimating". <br />