SECTION 01660 — EQUIPMENT TESTING AND SYSTEM STARTUP <br />PART 1 — GENERAL <br />1.1 GENERAL <br />A. Equipment testing and system startup are requisite to satisfactory completion of the <br />contract and, therefore, shall be completed within the contract time. <br />1.2 EQUIPMENT TESTING <br />A. The CONTRACTOR shall be responsible for scheduling all operations testing. The <br />CONTRACTOR is advised that the ENGINEER and the CITY's operating personnel <br />will witness operations testing and that the manufacturer's representative shall be <br />required to instruct the CITY's operating personnel in correct operation and <br />maintenance procedures. Such instruction shall be scheduled at a time arranged with <br />the CITY at least 2 weeks in advance and shall be provided while the respective <br />manufacturer's equipment is fully operational. Qualified persons who have been <br />made familiar in advance with the equipment and systems in the plant shall give on - <br />site instruction. Prior to scheduling any operations testing, the CONTRACTOR shall <br />have previously furnished the Owner's Manuals required under Section 01300. <br />B. The CONTRACTOR shall notify the ENGINEER at least 3 days in advance of each <br />equipment test. <br />C. The CONTRACTOR shall furnish all personnel, power, and all other necessary <br />equipment, facilities, and services required for conducting the tests. <br />1.3 SYSTEM STARTUP <br />A. The CONTRACTOR shall coordinate the startup and testing of the Security <br />Management System. <br />B. It is not the intent of the ENGINEER to instruct the CONTRACTOR in the startup of <br />the system; however, the ENGINEER will be available prior to and during startup to <br />provide technical support to the CONTRACTOR. <br />C. The CONTRACTOR shall immediately correct all defects in materials or workmanship <br />that appear during this test period. Time lost for equipment repairs, wiring corrections, <br />control point settings, or other reasons which actually interrupt the startup may, at the <br />discretion of the ENGINEER, be justifiable cause for extending the startup test <br />duration. <br />D. During the startup, the CONTRACTOR shall keep records of the operations, in <br />accordance with the instructions of the ENGINEER. <br />1.3 THIRTY DAY ACCEPTANCE TEST <br />City of Santa Ana Equipment Testing and System Startup <br />Security Management System Project Page 01660-1 <br />SantaAna_SMS_01660 <br />