<br />\... <br /> <br />\.,., <br /> <br />\.,. <br /> <br />Project Schedule, Contractor shall inform the City in <br />writing of the potential delay no less than thirty (30) days <br />prior to the scheduled event. Contractor's written <br />notification of the potential delay shall include a proposed <br />recovery plan for the City's consideration and approval. <br />The City's approval of such recovery plan shall not be <br />unreasonably withheld. If the City approves the <br />Contractor's recovery plan, damages relating to the delay <br />shall only apply to the newly adjusted Project Schedule. <br /> <br /> <br />Primary Agreement <br /> <br />Page 14 <br />