Exhibit 1
<br />CONTRACT CURRRENT
<br />SITE ALLOWANCE SOV BUDGET
<br />DEMOLITION, SHORING, EARTHWORK & GRADING $848,490 $257,878
<br />SITE UTILITIES $221,750 $245,800
<br />ASPHALT PAVING $108,378 $8,000
<br />LANDSCAPE, IRRIGATION $92,900 $750
<br />SITE CONCRETE $59,720 $0
<br />PARKING STRUCTURE
<br />CRACK CONTROL ALLOWANCE $2,500 $0
<br />FIELD ENGINEERING $6,000 $0
<br />SECURITY FENCING OUTSIDE GARAGE FOOTPRINT EXCLUDED EXCLUDED
<br />EXCAVATION & BACKFILL $58,233 $60,000
<br />PILES-DRIVEN/ POURED EXCLUDED EXCLUDED
<br />SITE CONCRETE /STAIRS $33,000 $0
<br />PARKING LOT STRIPING I BUMPERS $7,500 $10,000
<br />REINFORCING STEEL & PT $500,614 $822,000
<br />BARRIER CABLE $25,475 $25,000
<br />CONCRETE FORM $1,440,708 $1,444,990
<br />MASONRY $72,908 $332,604
<br />STEEL MISCELLANEOUS $274,337 $177,923
<br />SHEE7 METAL $3,784 $7,000
<br />CAULKING & BGWP $7,642 $18,000
<br />METAL DOORS /FRAMES (HARDWARE $3,100 $10,000
<br />OVERHEAD DOORS $10,000 $60,000
<br />GLASS & GLAZING $7,200 $15,800
<br />LATH & PLASTER $39,278 $106,000
<br />CERAMIC TILE $4,200 $5,000
<br />PAINTING $17,840 $101,000
<br />SIGNS & GRAPHICS $3,200 $10,000
<br />TOILET PARTITIONS /ACCESSORIES NIA NIA
<br />SPECIALTIES & EQUIPMENT N!A N/A
<br />PARKING CONTROLS (ALLOWANCE) $30,000 $826,336
<br />ELEVATORS $58,539 $50,000
<br />FIRE SPRINKLER SYSTEM !EXTINGUISHERS $38,300 $54,000
<br />PLUMBING $86,170 $85,000
<br />HVAC $5,135 $5,000
<br />ELECTRICAL $164,478 $242,750
<br />FINAL CLEAN-UP $4,923 $24,196
<br />TEMP POWER $10,000 $10,000
<br />CONTINGENCY $200,000 $100,000
<br />SUBCONTRACTORS FEE & GENERAL CONDITIONS $356.089 $374.452
<br />
<br />NEW WORK
<br />Page 1
<br />
|