Laserfiche WebLink
EXHIBIT B <br />TIME LINE ESTIMATE FOR MYRTLE AND RAITT AFFORDABLE HOMES <br />CIVIC CENTER BARRIO HOUSING CORP. <br />August 26, 2007 <br />(revision #3) <br />9/1/07-9/15/07 City approval of Civil and Architectural Contract <br />9/15/07 Begin topographic and boundary survey <br />10/15/07 <br />Survey completed and drafted in CAD format <br />10/16/07 <br />Begin Site Planning and Schematic Design <br />11/7/07 <br />Initial Concept review by Client (site plan, concept unit plans) <br />11/17/07 Second review by Client, approval of site plan and unit plans <br />11/21/07 Third review by Client, concept elevations, landscape plan <br />12/1/07 Meeting with planning and community development <br />12/8/07 Submit for site plan review <br />1/8/08 Public Hearing (assume approval, neighborhood meetings between submittal and public <br />Public Hearing) <br />1/15/08 Project cost estimate contract approval by City <br />2/1/08 Construction/project cost estimate <br />3/1/08 Obtain conditional financing approval, private and public <br />4/1/08 Begin Development and Disposition Agreement process between City and CCBHC <br />4/1/08 Begin Design Development and Construction Documents <br />5/15/08 Complete DDA process and submit to City Agency and Council (assume approval) <br />6/15/08 Building Department Submittal <br />8/1/08 Plan check approval <br />9/1/08 Submit Bid Document to City, prior to opening bid process <br />10/15/08 General Contractor Bid and Contract approval by City, CCBHC Board and Financial <br />Institution <br />11/15/08 General Contractor and CCBHC begin initial planning for construction start, permits, etc. <br />12/10/08 Begin Construction <br />