Laserfiche WebLink
1. :'1,' <br /> T CITY OF SANTA ANA <br /> ' PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> it /F s. <br /> OB <br /> Project Number Project No. 22-2764 Santa Ana Zoo—Walkway Improvements Change Order Number 1 <br /> Project—Phase 1 <br /> To Horizons Construction Company International, Inc. Contractor <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE:THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> The compensation both time and cost set forth in this change order comprises the total compensation due the <br /> Contractor, all Subcontractors, and all Suppliers for all work performed per this change order, including impact <br /> on unchanged work. By signing this change order, the Contractor acknowledges and agrees on behalf of <br /> himself, all Subcontractors, and all Suppliers, that the stipulated compensation includes payment for all work <br /> contained in this change order, plus all payment for interruption of schedules, extended field overhead, home <br /> office overhead, profit, delay, and all impact, ripple effect or cumulative impact on all other work under this <br /> Contract. The signing of this change order constitutes full mutual accord and satisfaction for all changes and <br /> work performed on this project, and that the time and cost paid per this change order constitutes the total <br /> equitable adjustments owed the Contractor, all Subcontractors, and all Suppliers for all work performed on <br /> this project. The Contractor on behalf of himself, all Subcontractors, and all Suppliers agrees to waive all <br /> rights, without exception or reservation of any whatsoever to file any further claim related to this project. <br /> TOTAL COST THIS CHANGE ORDER: DECREASE $ INCREASE $ 18,607.74 <br /> By reason of this order the CONTRACT TIME completion will be adjusted as follows: Six(6)Working Days <br /> We the undersigned contractor have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide <br /> all equipment,furnish all materials,except as may otherwise be noted above,and perform all service necessary for the work above specified,and will accept <br /> as full payment therefor the prices shown above. <br /> Accepted,Date 09/25/2025 Contractor Horizons Construction Company International, Inc. <br /> By Title <br /> Project Manager <br /> Approval recommended by Date Ad/7ZS <br /> LIC W GENCY EXEC E DIRECTOR <br /> Approved by Date 16(15(7-10-ar--- <br /> CITY MANAGER <br /> 1 <br /> _ �. _• c� <br /> Attest: �jr` _;, , Date <br /> TYCLERK • <br /> r. r <br /> Page 2 of 2 <br />