Bella Vista/Casa Bonita
<br />Water Main Improvements
<br />October 6, 2008
<br />Page 2
<br />NAME OF BIDDER
<br />1. J. DeSigio Construction, Inc.
<br />2. Dominguez General Engineering
<br />3. John T. Malloy, Inc.
<br />4. Majich Bros., Inc.
<br />5. J.A. Salazar Construction & Supply
<br />6. Southern California Pipeline
<br />7. GCI Construction, Inc.
<br />8. West Valley Construction Co., Inc.
<br />9. Leatherwood Construction, Inc.
<br />10. VCI Telecom, Inc.
<br />11. Garcia Juarez Construction, Inc.
<br />12. Alliance Streetworks, Inc.
<br />13.MNR Construction, Inc.
<br />14. BNB Engineering, Inc.
<br />CITY BID AMOUNT
<br />Arcadia $1,362,651.00
<br />Rosemead $1,373,388.00
<br />Los Angeles $1,397,497.00
<br />Altadena $1,460,546.00
<br />La Habra Heights $1,476,001.40
<br />Tustin $1, 506, 937.00
<br />Costa Mesa $1,525,716.00
<br />San Jose $1,558,295.00
<br />Fountain Valley $1,564,266.00
<br />Upland $1, 636, 573.00
<br />Brea $1,697,255.00
<br />Anaheim $1,739,277.00
<br />San Dimas $2, 099, 580.00
<br />Santa Ana $2,301,876.00
<br />A total of 14 bids were received and all were responsive. The lowest bid
<br />was submitted by J. DeSigio Construction, Inc. for $1,362,651, which is
<br />below the Engineer's estimate of $1,700,000.
<br />ENVIRONMENTAL IMPACT
<br />In accordance with the California Environmental Quality Act, the
<br />recommended action is exempt from further review. Categorical exemption,
<br />ER No. 2008-97, has been filed.
<br />FISCAL IMPACT
<br />The funding analysis shows a total estimated construction cost of
<br />$1,703,300, for the project (Exhibit 2). Funds are available in the
<br />Water Utility Capital Projects fund {account no. 66-579-6635).
<br />APPROVED AS TO FUNDS AND ACCOUNTS:
<br />v ~~ ,~
<br />James G. ss Francisco Gutierrez t
<br />Executive Director Executive Director
<br />Public Works Agency Finance & Mgmt. Services Agency
<br />23D-2
<br />
|