LSA ASSOCIATES, INC. <br />JULY 2010 <br />INITIAL STUDY/MITIGATED NEGATIVE DECLARATION <br />FIRST STREET BRIDGE REPLACEMENT PROJECT <br />CITY OF SANTA ANA <br />Dry and Wet Season Activities <br />All demolition activities and some construction activities will take place only in the dry season (April <br />15 to October 15 annually) due to seasonal constraints of working in the riverbed. Therefore, <br />construction may take up to two dry seasons to complete the new bridge. Specific construction <br />activities such as demolition of the piers, foundation elements, and upper parts of the bridge will be <br />conducted only during the dry season. Construction activities that encompass replacement and <br />reconstruction of the parts of the bridge above bridge elevation (placing girders, deck construction) <br />may be conducted during the wet season because they will not take place in the riverbed. <br />Bicycle Detour Plans <br />The Santa Ana River Bicycle Trail will not close due to construction. However, detours will be <br />necessary while construction takes place. The bicycle trail detour plans are described below and <br />shown in Figures 14, 15 and 16. <br />Phase 1: Bicycle Detour for Closure of the Trail Access Ramp on North Side of First <br />Street. During Stage 1, when construction of the north side of the bridge occurs, the <br />northside Bicycle Trail access on First Street will be temporarily closed. Therefore, cyclists <br />on the Bicycle Trail exiting and traveling westerly on First Street will have to exit either at <br />McFadden Avenue or Fifth Street, depending on whether they are traveling north or south on <br />the Bicycle Trail. Cyclists exiting onto First Street and traveling easterly will still be able to <br />do so by using the south side Bicycle Trail access. Cyclists wanting to enter the Bicycle Trail <br />from the east will be routed along these same paths to gain access to the Bicycle Trail. <br />Phase 2: Bicycle Detour for Closure of the Trail Access Ramp on South Side of First <br />Street. During Stage 2, when construction of the south side of the bridge occurs, the south <br />side Bicycle Trail access on First Street will be temporarily closed. Therefore, cyclists on the <br />Bicycle Trail exiting and traveling eastbound on First Street will have to use the Fifth Street <br />exit. Cyclists exiting onto First Street and traveling westbound will still be able to do so by <br />using the northside Bicycle Trail access. Cyclists wanting to enter the Bicycle Trail from the <br />west will be routed along these same paths to gain access to the Bicycle Trail. <br />Detour For Overhead Construction Activities. The Bicycle Trail will remain open along <br />the channel during both Phase 1 and Phase 2; however, certain construction activities which <br />would pose a hazard to Bicycle Trail uses such as demolition of the existing bridge and <br />erection of the precast girders for the new bridge will require a temporary detour of the <br />Bicycle Trail. It is expected that each stage will require two separate detours for an estimated <br />duration of one week each for these activities. During these activities, both northbound and <br />southbound cyclists on the Bicycle Trail will have to exit prior to First Street at either <br />McFadden Avenue (northbound) or Fifth Street (southbound) and then re-enter the Bicycle <br />Trail at the next entrance (McFadden Avenue or Fifth Street). <br />PADMJ0701\MND\2.0 Project Description.doc (07/25/10) <br />2-18 <br />20A-29