<br />Twelve vendors requested bidding documents, and a total of 12 bids were received. No
<br />bids were received from Santa Ana vendors.
<br />As legally required, a Notice Inviting Bids was advertised in the Orange County Register
<br />newspaper on September 18, 2025 and September 25, 2025. The project was also
<br />advertised on PlanetBids from September 18, 2025 through October 9, 2025. Bids were
<br />received electronically via PlanetBids on October 9, 2025.
<br />Bid Results Summ
<br />RANK
<br />BIDDER'S NAME
<br />LOCATION
<br />BASE BID
<br />1
<br />RCCI
<br />Azusa, CA
<br />$5,716,266.00
<br />2
<br />Armstrong Cal Builders Inc.
<br />Stanton, CA
<br />$6,382,620.00
<br />3
<br />Boudreau Pipeline Corporation
<br />Woodland Hills, CA
<br />$7,675,383.00
<br />4
<br />GMZ Engineering, Inc.
<br />Westlake Village, CA
<br />$7,859,525.00
<br />5
<br />Legion Contractors Inc.
<br />Los Angeles, CA
<br />$7,866,800.00
<br />6
<br />mmc, inc
<br />La Palma, CA
<br />$8,476,150.00
<br />7
<br />Zusser Company, Inc.
<br />Los Angeles, CA
<br />$8,976,488.00
<br />8
<br />Environmental Construction, Inc.
<br />Woodland Hills, CA
<br />$9,521,407.00
<br />9
<br />Lonerock, Inc.
<br />Irvine, CA
<br />$9,627,255.00
<br />10
<br />Caliagua, Inc.
<br />Anaheim, CA
<br />$9,803,623.00
<br />11
<br />Mike Bubalo Construction Co.,
<br />Inc.
<br />Baldwin Park, CA
<br />$9,917,900.00
<br />12
<br />Green Building Corporation
<br />North Hollywood, CA
<br />$9,951,482.00
<br />A total of 12 bids were received. RCCI, the lowest bidder, was deemed non -responsive
<br />for failing to include a comprehensive list of subcontractors as required by the project
<br />specifications. Armstrong Cal Builders Inc. submitted the lowest responsive base bid in
<br />the amount of $6,382,620 (Exhibit 4). As specified in the bid documents, the lowest bid
<br />shall be determined by the Base Bid.
<br />In the past five years, Armstrong Cal Builders Inc. has completed construction of the
<br />Santiago Park Main Entrance Project for the Public Works Agency. Based on the bid
<br />analysis and a contractor reference check, Staff recommends awarding a construction
<br />contract to Armstrong Cal Builders Inc. in the amount of $6,627,620 for the Base Bid
<br />and additional Bid Alternative for construction of the Santa Ana Zoo Stormwater
<br />Capture and Diversion Project (Exhibit 5). The Bid Alternative item is a flow meter and