PROJECT TITLE:
<br />Alley Improvement Program
<br />PROJECT CATEGORY:
<br />Street Improvements
<br />Allev Rehabilitation
<br />LOCATION MAP
<br />CITYWIDE
<br />AGENCY:
<br />Public Works
<br />A
<br />CITY OF SANTA ANA FY 25126CIP
<br />CAPITAL IMPROVEMENT PROJECT WORKSHEET
<br />PROJECT DESCRIPTION:
<br />This project will provide for the removal of existing damaged pavement
<br />and reconstruction with Portland Cement Concrete (PCC) for alleys
<br />citywide.
<br />L
<br />PROJECT NEED:
<br />The Citywide network of Portland Cement Concrete (PCC) and asphalt alleys
<br />is in extreme state of deterioration with the presence of numerous potholes,
<br />cracking, spalling, and uplifting. PCC pavement will eliminate the drainage
<br />problems associated with the asphalt pavement and provide a longer life for
<br />the alleys.
<br />PROJECT COSTS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
<br />Construction 1,389,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000
<br />Engineering 111,000 - - - - - -
<br />TOTAL 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000
<br />SOURCE OF FUNDS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
<br />GENERAL FUND 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000
<br />DIVISION:
<br />CIP Engineering
<br />i
<br />TOTAL 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000
<br />CONTACT:
<br />Jason Gabriel, Principal Civil Engineer
<br />DATE:
<br />11-Dec-2025