Laserfiche WebLink
Request for Approval of Change Order No. 1 <br />Project 09 -1752 <br />Request for Approval of Change Order No. 1 <br />December 30, 2002 <br />Page 2 of 2 <br />During excavation for the precast water vault it was discovered that the proposed <br />vault location would be in conflict with a proposed SCE transmission and <br />distribution pole. It was recommended to re- position the new vault approximately 25 <br />feet to the east. Due to this change, the contractor incurred additional costs for re- <br />excavation, backfilling the original excavation and additional pipes and fittings. <br />(PCO 2) Prior approval was obtained on October 12, 2011. <br />AGREED COST = $11,544.77 <br />3. On the eastside of Bristol Street, south of Warner Avenue, there were two existing <br />private backflow devices. Due to the street widening the devices needed to be <br />relocated outside of the City's new right -of -way. (PCO 3) Prior approval was <br />obtained on September 12, 2011. <br />AGREED COST= $3,680 <br />APPROVED AS TO FUNDS AND ACCOUNTS: <br />Raul Godinez II, bdcutive Director Francisco Gutierrez, Executive Director <br />Public Works Agency Finance and Management Services Agency <br />Klconstniction\projects\0 9-1752 \MEM RFA 01 CCO 1 <br />