Laserfiche WebLink
EXHIBIT B <br />SCOPE OF SERVICES <br />1. SCOPE OF WORK <br />The Request for Proposals calls for removal and disposal of existing luminaries; furnishing and installing <br />new LED street lights and all testing, including photometric, to prove that furnished luminaries perform <br />as specified. <br />The Contractor shall provide at its own risk and cost all labor, materials, tools, equipment, and traffic <br />control per the Work Area Traffic Control Handbook ("WATCH"), transportation, hauling, dumping, and <br />recycling of removed material as part of this project. The City reserves the right to salvage existing <br />luminaries. All salvaged luminaries shall be delivered to the City Corporate Yard at no cost to the City. <br />II. FUNCTIONS AND RESPONSIBILITIES <br />A. DIRECTOR <br />The Director shall have the authority to accept/reject materials, workmanship and to make minor <br />changes in work or schedule. When the performance of the work or completion per schedule is <br />determined to be substandard, Director may 1) recommend that all or a portion of payment be <br />withheld, and/or forfeiture for delay be assessed; 2) direct the work be accomplished by a separate <br />contractor, in order to complete the necessary work as close to schedule as possible and withhold the <br />resulting costs. Payment to be withheld shall be deducted from the next monthly payment due to the <br />Contractor, or if the amount is insufficient to cover payment, the Contractor shall be liable and will be <br />billed accordingly. <br />The Director or his authorized representative shall decide all questions, which may arise as to the <br />manner of performance and completion per schedule, acceptable fulfillment of the contract by the <br />Proposer, interpretation of the specifications, and compensation to include completion of work by <br />alternate sources. <br />B. CONTRACTOR <br />1. Local Office <br />Contractor shall maintain a local office with a competent representative who can be reached <br />during normal working hours and authorized to discuss matters pertaining to this contract with the <br />Director. Contractor will not be allowed to store equipment or materials at any contracted area. <br />2. Submittals <br />Contractor shall submit to the Director at the beginning of work, 1) a detailed job <br />schedule, 2) names and titles of all persons working on the project, and 3) materials to be <br />used on the project for approval. All submittals shall be periodically updated as <br />10 <br />25F-17