Laserfiche WebLink
COMMENTS <br />PROJECT OVERALL PERCENTAGE OF COMPLET /ON <br />We currently estimate the project's overall percentage of completion at 67 %. <br />CHANGE ORDERS (OCOs) <br />FYI -Given the subject building's age, scope of the proposed renovations and expected "unforeseen" <br />added improvements, typically associated with this type of product, we anticipate a significant amount <br />of cost impacting scope changes to surface during the early phases of construction. We expect the <br />change orders will significantly subside once all the "unforeseen" have been identified. From that <br />point on, project change orders most likely will involve Owner requested improvements. <br />Current Chance Order <br />Included in the contractor's current payment application request is Owner approved Change Order # <br />1 O, totaling $19,828 (pre- approved by all parties at last month's draw meeting). Change Order # 1 O is <br />comprised of 3 PCIs, consisting primarily of added Garden Roof waterproofing and minor <br />miscellaneous items. No time extensions are included in current change order. We take no <br />exception to the content or costs associated with a// change orders approved to date. Please refer to <br />Approved Change Orders for a list of "approved" project change orders submitted to date. <br />PEND /NG 8 POTENT /AL CHANGE /TEMS (PC /s) <br />Approved for submittal in next month's payment application is pending Change Order # 11 , totaling <br />$79,5128. Change Order # 11 is comprised of 6 PCIs, consisting primarily of additional fire <br />department changes (ratings) and several miscellaneous Owner requested improvements. <br />HARD COST CONTINGENCY <br />Latest Sources and Uses of Funds indicate an infusion of $448, 639 into the project's origins/ hard <br />cost contingency budget. <br />Our understanding of the project's hard cost contingency budget is as fo / /ows: <br />Origins/ Hard Cost Contingency Budget: <br />Added Hard Cost Contingency Funds: <br />Revised Hard Cost Contingency Budget. <br />Change Orders Approved To Oate: <br />Committed Contingency Funds <br />$ �, 643, � 02 <br />$ 448, 639 <br />$ 2,099,749 <br />$ 9, 389, 700 (Through Change Order # 90 ) <br />$ 9, 389, 700 (66% of contingency budget ) <br />Remaining Hard Cost Contingency funds: $ 702, 049 (34 % of contingency funds <br />remaining ) <br />CONSTRUCT /ON SCHEDULE <br />Assuming no additional last minute City changes to the City approved scope of work, we currently feel <br />the contractor's 11/14/1 O estimated completion date (TCO) remains feasible. By the end of July, we <br />will be in a better position to evaluate the reasonableness of the contractor's estimated completion <br />date. <br />