Request for Approval <br />May 23, 2013 <br />Project Nos. 12 -6753, <br />Page 2 <br />of Change Order No. 2 <br />12 -7531 & 11 -2618 <br />CHANGE ANALYSIS <br />DETAILED JUSTIFICATION <br />This project is split into two stages; Phase 16 of the City's Residential Street Repair <br />and the Santiago Park Roadway Improvements. <br />Phase 16 City Residential Street Repair Project addresses the remaining asphalt <br />streets that were identified as part of the Residential Street Repair Program. These <br />segments of local streets were identified as a high priority for rehabilitation in the <br />City's pavement management system. <br />Santiago Park Roadway Improvements addresses the service and access roads in <br />and around Santiago Park. These roads provide access to the wildlife and <br />watershed center, nature reserve, the archery range and access for City staff to <br />water production facilities. <br />This Change Order is entirely within the Santiago Roadway Improvements phase of <br />the project and encompasses modifications to the wrought iron fence, addition of a <br />decomposed granite walkway and pressure treated wood parking stops in Santiago <br />Park. A prior approval was granted for this work on December 10, 2012. This work <br />was done partially under contract bid items and partially on a time - and - material <br />basis. <br />The work included clearing and grubbing, relocation of existing irrigation heads, <br />construction of a decomposed granite trail, and installation of pressure treated <br />beams to create a barrier between pedestrians and vehicular traffic. A small portion <br />of this extra work was done using contract bid items; the majority of the extra work <br />was done on a time - and - materials basis. <br />REVISED DETAILS <br />Contract Section <br />Revised Section <br />6 0" <br />H I MODIFIED DETAIL W /WALK <br />