<br /> <br /> Project 06-1500 <br /> RFA Change Order No. 5 <br /> February 8, 2012 <br /> Page 2 <br /> <br /> <br /> 2. In order to prevent loose gravel from entering the nearby catch basin at the northeast <br /> corner of Bristol Street and McFadden Avenue, the contractor was directed to remove <br /> three inches of gravel and pave the area with three inches of asphalt. The work also <br /> added a concrete curb that will address the gap between the existing grade and bottom <br /> of chain link fence. This work was done on time and materials. This work was done on a <br /> time-and-materials basis. <br /> <br /> AGREED COST = $17,560 <br /> 3. The synthetic turf area in the linear park near the Highland Street cul-de-sac along the <br /> east side of Bristol Street was being used for open-park like activities for which it was not <br /> designed; therefore the new turf was being damaged. In order to discourage this type of <br /> heavy use and prolong the lifespan of the turf, the contractor was directed to install six <br /> London Plane Sycamore trees with irrigation in this area. This work was done on a time <br /> and materials basis. <br /> <br /> FINAL COST = $12,772 <br /> 4. When the proposed natural turf was replaced by artificial turf, the irrigation for that <br /> portion of the project was deleted and a credit was issued to the contract. Subsequently, <br /> it was necessary to add a bubbler irrigation system to water the trees planted within the <br /> artificial turf area. This work was done on a time and materials basis. <br /> <br /> FINAL COST = $25,500 <br /> <br /> 5. During construction of the M.W.D. vault extension, M.W.D. requested adding temporary <br /> power and additional wiring and circuits for the flow monitoring equipment. This required <br /> new electrical permits causing delays to the project. This compensates the contractor for <br /> costs incurred for the delays. <br /> FINAL COST = $16,562 <br /> <br /> <br /> APPROVED AS TO FUNDS AND ACCOUNTS: <br /> n, <br /> <br /> Rau Godinez, II Francisco Gutierrez r <br /> Executive Director Executive Director <br /> Public Works Agency Finance and Management Services Agency <br /> <br /> <br /> K:\Construction\Projects\06-1500\Change Orders\06-1500 RFA CO 5.doc <br />