PART II SPECIFICATIONS <br />EXCAVATING AND BACKFILLING <br />Excavating and backfilling shall conform to Section 86.2.01, "Excavating and Backfilling"of the <br />California State Specifications (CSS) and these Special Provisions. <br />The following paragraph shall be added to Section 86-2.01: <br />All excavated material in roadway shall be removed from the site and backfilled with compacted crushed <br />aggregate base material topped with temporary asphalt concrete on the same working day as removed. A <br />temporary alternative to backfilling, with permission of the Agency, shall be the placement of steel plates <br />with temporary asphalt concrete ramping at edges of the steel plates. Such plating shall not be allowed <br />for more than five (5) working days, after which backfill shall be required. <br />Slurry backfill: Use of a one -sack cement and sand slurry provided by a commercial ready -mix concrete <br />vendor may be permitted except in parkway areas. The slurry shall be placed monolithic from the bottom <br />of the excavation to the bottom of the existing structural section or sidewalk; or as directed by the <br />Agency. <br />CONDUIT <br />Roadway lighting conduit shall conform to the provisions in Section 86-2.05, "Conduit", of CSS and these <br />Special Provisions. <br />Roadway lighting conduit shall be schedule 80 PVC unless shown otherwise on the plans. Insulated bonding <br />bushings will be required. <br />All conduits, excluding SCE service conduits, shall be installed at the depth not less than 42" below <br />finished grade in pavement areas 24" in sidewalk and parkway areas. Only when conduits are to be <br />installed between adjacent pull boxes, from street light pole to pull box or pull box to cabinet where the <br />in-between distance is too short to meet the 42" depth and the 45 -degree sweep requirements, the conduit <br />may be installed at lower depth but not less than 18" below finished grade. <br />After conductors have been installed, the ends of conduits shall be sealed with industry grade sealing <br />compound. <br />Replace sidewalk and pavement in-kind to match existing material, color, and pattern, from score mark to <br />score mark after pull boxes and conduit have been installed. Payment for replacement of sidewalk, <br />pavement, hardscape and landscaping shall be included in lump sum price. All costs for potholing, <br />trenching, boring etc shall be included in lump sum price. <br />PULL BOXES <br />Pull boxes shall conform to the provisions in Section 86-2.06, "Pull Boxes" of CSS, CSP ES -8 and these <br />Special Provisions. Notes 4(a)(5) and 4(b)(10) on CSP ES -8 shall not apply. <br />Pull box size shall be Number 5 except where shown otherwise on the plan or as directed by the Agency. <br />Bottoms shall be bedded in crushed rock. Pull boxes shall not be grouted. Pull boxes shall be polymer <br />concrete reinforced with heavy -weave fiberglass. Pull box covers shall be lightweight (BES lite non - <br />concrete, or approved equal). Pullbox lids shall be stamped "LIGHTING". <br />New pull boxes shall not be installed within any curb access ramp. <br />